7743 N CHERRYSTONE AVE 91402
Certificate Information: 7743 N CHERRYSTONE AVE 91402
- Application / Permit
- 21014-20000-01255
- Plan Check / Job No.
- B21VN03090
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 15'-9" X 31'-4" ADDITION AND REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 3/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | LUIS RINCON |
| Corrections Issued | 3/17/2021 | LUIS RINCON |
| Applicant returned to address corrections | 4/5/2021 | RAPHAEL ROSAS |
| Issued | 4/21/2021 | APPLICANT |
| Building Plans Picked Up | 4/22/2021 | APPLICANT |
| CofO in Progress | 3/6/2025 | VINCENT HANLEY |
| Permit Finaled | 3/17/2025 | RUBEN SALAS |
| CofO Issued | 3/17/2025 | RUBEN SALAS |
| Permit Finaled | 3/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/17/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/4/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/11/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 5/18/2021 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/24/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/27/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/27/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/14/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 6/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 6/14/2021 | Partial Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | MARK JOHNSON |
| HVAC-Rough | 6/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| Insulation | 6/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 6/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| Insulation | 6/23/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Shower Pan | 6/23/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 6/25/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/25/2021 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/25/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 6/25/2021 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/25/2021 | Approved | JAVIER RAMOS JR |
| Insulation | 6/29/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/29/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Shower Pan | 6/29/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 6/30/2021 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 6/30/2021 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 7/2/2021 | Corrections Issued | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/2/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/21/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 12/21/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/21/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 12/21/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 12/21/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/21/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 12/21/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/25/2022 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Approved | GREGG CUMMINGS |
| Special/Order Compliance | 8/25/2022 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 2/27/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/27/2025 | Approved | VINCENT HANLEY |
| Final | 2/27/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Final | 2/27/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/27/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 2/27/2025 | Approved | VINCENT HANLEY |
| Final | 3/6/2025 | OK to Issue CofO | VINCENT HANLEY |