1838 1\2 W 70TH ST 90047

Certificate Information: 1838 1\2 W 70TH ST 90047

Application / Permit
21014-20000-01224
Plan Check / Job No.
B21VN03019
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ECPC: ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/18/2021
Issuing Office
Current Status
CofO Issued on 1/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 RICHARD GARCIA
Corrections Issued 3/31/2021 RICHARD GARCIA
Plan Check Approved 11/2/2021 LUISANGEL VALENZUELA
Building Plans Picked Up 11/2/2021 APPLICANT
Issued 11/18/2021 APPLICANT
CofO in Progress 11/21/2022 ENRIQUE MIRELES
CofO in Progress 11/21/2022 ENRIQUE MIRELES
Permit Finaled 1/7/2023 DEROLD HAUFF
CofO Issued 1/7/2023 DEROLD HAUFF
Permit Finaled 1/7/2023 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 5/3/2021 PABLO ESTRADA
Address approval Cleared 5/6/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 5/6/2021 WALLIE JONG
Hydrant and Access approval Cleared 6/11/2021 KURT CORRAL
Construction near power lines Cleared 8/21/2021 RIDWAN HARDY
Construction within easement Cleared 8/21/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/27/2021 WALLIE JONG
Sewer availability Cleared 9/27/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/1/2022 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 3/3/2022 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 3/7/2022 Approved FREDDIE RIVERA
Underground Mechanical 3/17/2022 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 3/22/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 4/8/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Approved ENRIQUE MIRELES
Green Building Rough 4/8/2022 Approved ENRIQUE MIRELES
Insulation 4/21/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 4/21/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/25/2022 Approved ENRIQUE MIRELES
Drywall Nailing 5/18/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/7/2022 Approved ENRIQUE MIRELES
Final 9/7/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 9/7/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 9/7/2022 Approved ENRIQUE MIRELES
Final 11/14/2022 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 11/14/2022 Approved ENRIQUE MIRELES