8221 N LAURELGROVE AVE 91605

Certificate Information: 8221 N LAURELGROVE AVE 91605

Application / Permit
21014-20000-01223
Plan Check / Job No.
B21VN03016
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL EX. SFD. CREATE TWO NEW BEDROOMS AND BATHROOM AT EX. FAMILY ROOM. WORK PER ENGINEER.
Permit Issued
Issued on 6/21/2022
Issuing Office
Current Status
Permit Finaled on 8/29/2022

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 ALFREDO JARA
Corrections Issued 3/31/2021 ALFREDO JARA
Applicant returned to address corrections 4/15/2022 ROSENDO MEDINA
Applicant returned to address corrections 5/13/2022 MOHAMMAD ESMAILI
Plan Check Approved 6/21/2022 ROSENDO MEDINA
Issued 6/21/2022 APPLICANT
Building Plans Picked Up 6/23/2022 APPLICANT
Permit Finaled 8/29/2022 MATTHEW NELSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/5/2021 GILBERT URREA
Roof/Waste drainage to street Cleared 11/24/2021 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 11/30/2021 AMIR KASHFI
Sewer availability Cleared 11/30/2021 AMIR KASHFI
Address approval Cleared 5/13/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/8/2022 Conditional Approval MICHAEL SMITH
Deputy Wood Construction 7/11/2022 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 7/12/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 7/12/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/12/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Wood Frame 7/12/2022 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 7/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 7/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/19/2022 Approved CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 7/20/2022 No Result Entered ADRIAN GAUTHIER
BUILDING-Rough-Frame 7/21/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 7/21/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 7/21/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 7/21/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/29/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 7/29/2022 Approved CHRISTOPHER DELLEFIELD
Final 8/29/2022 Permit Finaled MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 8/29/2022 Approved MATTHEW NELSON