8744 W SKYLINE DR 90046
Certificate Information: 8744 W SKYLINE DR 90046
- Application / Permit
- 21014-20000-01216
- Plan Check / Job No.
- B21VN03001
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 495sf UNDERFLOOR AREA TO (E) SINGLE FAMILY DWELLING; CHANGE WINDOWS AND DOORS, RE-STUCCO; RE ROOF
- Permit Issued
- Issued on 12/21/2021
- Issuing Office
- Current Status
- CofO Issued on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | CHON CHIO KUO |
| Corrections Issued | 4/21/2021 | CHON CHIO KUO |
| Quality Review Completed | 4/21/2021 | STEVEN KIM |
| Applicant returned to address corrections | 6/21/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/30/2021 | SELLA BENYAMIN |
| Plan Check Approved | 11/12/2021 | SELLA BENYAMIN |
| Issued | 12/21/2021 | APPLICANT |
| CofO in Progress | 12/7/2023 | RAUL BARAJAS |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
| CofO Issued | 12/7/2023 | DEROLD HAUFF |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/6/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/6/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2021 | DINAH GARIN |
| ZI | Cleared | 10/15/2021 | OLGA AYALA |
Contact Information
| No Data Available. |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/23/2022 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/23/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 8/23/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Light Gage Steel Frame | 8/23/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 8/23/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Inspection | 8/23/2022 | Partial Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 8/23/2022 | Corrections Issued | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 8/23/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Inspection | 9/7/2022 | Partial Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 9/7/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 9/7/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 9/13/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/27/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/27/2022 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 9/27/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 9/27/2022 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 9/27/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 9/27/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 9/29/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 10/4/2022 | Corrections Issued | RAUL BARAJAS |
| Wood Frame | 11/2/2022 | Corrections Issued | RAUL BARAJAS |
| Drywall Nailing | 11/4/2022 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 11/8/2022 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 11/8/2022 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 11/8/2022 | Corrections Issued | RAUL BARAJAS |
| Wood Frame | 11/8/2022 | Partial Inspection | RAUL BARAJAS |
| Gas Test | 11/18/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/11/2023 | Partial Approval | RAUL BARAJAS |
| Final | 9/11/2023 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/11/2023 | Approved | RAUL BARAJAS |
| Green Building Final | 9/11/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 9/11/2023 | Corrections Issued | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 9/11/2023 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/1/2023 | Approved | RAUL BARAJAS |
| Final | 12/1/2023 | OK to Issue CofO | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/1/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 12/1/2023 | Approved | RAUL BARAJAS |