5841 E ARROYO DR 90042

Certificate Information: 5841 E ARROYO DR 90042

Application / Permit
21014-20000-01152
Plan Check / Job No.
B21VN02853
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
17'-2" x 24'-1" ADDITION TO THE REAR OF EXISTING SINGLE FAMILY DWELLING COMPLY WITH DEPARTMENT ORDER effective date 10/14/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 SELLA BENYAMIN
Corrections Issued 3/15/2021 SELLA BENYAMIN
Building Plans Picked Up 3/22/2021 APPLICANT
Applicant returned to address corrections 6/24/2021 SELLA BENYAMIN
Plan Check Approved 7/7/2021 SELLA BENYAMIN
Issued 9/1/2021 APPLICANT
CofO in Progress 5/29/2025 LILIANA PORTILLO
CofO in Progress 5/29/2025 LILIANA PORTILLO
Permit Finaled 6/5/2025 DEROLD HAUFF
CofO Issued 6/5/2025 DEROLD HAUFF
Permit Finaled 6/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/21/2021 WALLIE JONG
Sewer availability Cleared 4/21/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/23/2021 WALLIE JONG
Grading Pre-Inspection Cleared 6/24/2021 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2021 Corrections Issued PATRICK LIEBREGT
Pre-Inspection 6/21/2024 Corrections Issued JONATHAN FRANCHINI
Drywall Nailing 12/23/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 12/24/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 12/24/2024 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 3/6/2025 Approved LILIANA PORTILLO
Shower Pan 3/6/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/21/2025 Approved LILIANA PORTILLO
Final 5/21/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/21/2025 Approved LILIANA PORTILLO
Green Building Final 5/21/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 5/21/2025 Approved LILIANA PORTILLO
MERV13>=Final 5/21/2025 Approved LILIANA PORTILLO
MERV13>=Rough 5/21/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 5/21/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 5/27/2025 Approved LILIANA PORTILLO
Final 5/27/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 5/27/2025 Approved LILIANA PORTILLO
HVAC-Final 5/27/2025 Approved LILIANA PORTILLO
PLUMBING-Final 5/27/2025 Approved LILIANA PORTILLO
Smoke Detectors 5/27/2025 Approved LILIANA PORTILLO