17607 W BESSEMER ST 91316
Certificate Information: 17607 W BESSEMER ST 91316
- Application / Permit
- 21014-20000-01134
- Plan Check / Job No.
- B21VN02817
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF LAUNDRY ROOM, FULL BATHROOM, DINING ROOM (22'-3" X 19'-5") & PATIO COVER (14' X 17'-6") AT REAR OF (E) 1-STORY SFD W/ ATTACHED GARAGE PER ENG'R DESIGN
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/14/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/23/2021 | JENNIFER LEE |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| Applicant returned to address corrections | 2/9/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/31/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/23/2022 | NILOOFAR MEHRAIN |
| Issued | 6/24/2022 | APPLICANT |
| CofO in Progress | 8/16/2023 | JEFFREY PARD |
| Permit Finaled | 11/2/2023 | JOHN JANSON |
| CofO Issued | 11/2/2023 | JOHN JANSON |
| Permit Finaled | 11/2/2023 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 4/7/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 7/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/31/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/5/2022 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 9/7/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/29/2022 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 9/29/2022 | Partial Approval | SEAN HAUPT |
| Underground Mechanical | 9/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 12/7/2022 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 12/7/2022 | Approved | SEAN HAUPT |
| Insulation | 12/15/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/15/2022 | Approved | SEAN HAUPT |
| Shower Pan | 12/15/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 12/23/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 12/23/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/23/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 4/20/2023 | Approved | SEAN HAUPT |
| Final | 4/20/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 4/20/2023 | Approved | SEAN HAUPT |
| PLUMBING-Final | 4/20/2023 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/20/2023 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 4/20/2023 | Approved | SEAN HAUPT |
| Final | 8/15/2023 | OK to Issue CofO | JEFFREY PARD |