14258 W SAYRE ST 91342
Certificate Information: 14258 W SAYRE ST 91342
- Application / Permit
- 21014-20000-01123
- Plan Check / Job No.
- B21VN02786
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (N) MASTER BEDROOM/BATHROOM/HALLWAY (IRR 13' X 20'-6") & PATIO COVER (4' X 3'-9") TO (E) 1-STORY SFD PER WFPP
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 7/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/14/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/20/2021 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 10/27/2021 | APPLICANT |
| Issued | 11/2/2021 | APPLICANT |
| CofO in Progress | 7/1/2022 | ARAM AVEDISIAN |
| CofO Issued | 7/16/2022 | MICHAEL SMITH |
| Permit Finaled | 7/16/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/26/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 10/13/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 10/13/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | D H Property Maintenance Inc; Lic. No.: 985811-B | 11312 COVELLO STREET SUN VALLEY, CA 91352 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/16/2021 | Corrections Issued | JOHN HAYES |
| Special/Order Compliance | 11/29/2021 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 11/29/2021 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 12/6/2021 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 1/5/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 1/5/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/5/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 1/5/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/5/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 1/12/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 1/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 1/12/2022 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 1/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 1/18/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/18/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/19/2022 | Approved | JOHN HAYES |
| Green Building Rough | 1/19/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 1/19/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 1/26/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 1/26/2022 | Approved | JOHN HAYES |
| Final | 6/2/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 6/2/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 6/2/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/1/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 7/1/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 7/1/2022 | Approved | ARAM AVEDISIAN |