6033 W COMEY AVE 90034

Certificate Information: 6033 W COMEY AVE 90034

Application / Permit
21014-20000-01109
Plan Check / Job No.
B21VN02747
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2ND STORY ADDITION OF 899 SQFT & INTERIOR ALTERATION TO (E) 1ST FLR OF SFD NFPA-13D SPRINKLERS REQUIRED THROUGHOUT BUILDING
Permit Issued
Issued on 10/19/2021
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 PETER MOSESIAN
Corrections Issued 4/7/2021 PETER MOSESIAN
Quality Review Completed 4/21/2021 OMID HEDAYAT
Plan Check Approved 9/10/2021 PETER MOSESIAN
Issued 10/19/2021 APPLICANT
CofO in Progress 2/12/2024 MEL KHACHATOURIAN
Permit Finaled 2/17/2024 DANIEL ORRANTE
CofO Issued 2/17/2024 DANIEL ORRANTE
Permit Finaled 2/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/29/2021 JEANIE LAM
Sewer availability Cleared 5/5/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/11/2021 JEANIE LAM
Low Impact Development Cleared 8/26/2021 MITESH PATEL

Contact Information

Contractor Dosh Construction Inc; Lic. No.: 1064567-B 14721 OXNARD ST      VAN NUYS, CA 91411
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/16/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 2/24/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 2/24/2022 Corrections Issued EVAN COOPER
Green Building Rough 2/24/2022 Not Ready for Inspection EVAN COOPER
HVAC-Rough 2/24/2022 Corrections Issued EVAN COOPER
MERV13>=Rough 2/24/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 2/24/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 3/3/2022 Approved EVAN COOPER
HVAC-Rough 3/10/2022 No Access for Inspection EVAN COOPER
Insulation 3/10/2022 No Access for Inspection EVAN COOPER
Wood Frame 3/11/2022 Corrections Issued EVAN COOPER
Insulation 3/14/2022 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 3/22/2022 Conditional Approval EVAN COOPER
Interior/Exterior Lathing 3/22/2022 Corrections Issued EVAN COOPER
Insulation 3/25/2022 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 3/31/2022 Partial Approval EVAN COOPER
Drywall Nailing 4/1/2022 Approved EVAN COOPER
Green Building Rough 4/1/2022 Approved EVAN COOPER
Shower Pan 4/5/2022 Approved EVAN COOPER
Interior/Exterior Lathing 4/8/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 11/13/2023 Approved MEL KHACHATOURIAN
Final 11/13/2023 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 11/13/2023 Approved MEL KHACHATOURIAN
Green Building Final 11/13/2023 Approved MEL KHACHATOURIAN
MERV13>=Final 11/13/2023 Approved MEL KHACHATOURIAN
MERV13>=Rough 11/13/2023 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved MEL KHACHATOURIAN
Smoke Detectors 11/13/2023 Approved MEL KHACHATOURIAN
Final 2/13/2024 OK to Issue CofO MEL KHACHATOURIAN