7257 N RIVERTON AVE 91352

Certificate Information: 7257 N RIVERTON AVE 91352

Application / Permit
21014-20000-01107
Plan Check / Job No.
B21VN02730
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1ST & 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING WITH ENTIRELY ALL NEW FRAMING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/25/2023
Issuing Office
Valley
Current Status
Issued on 9/25/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 COLIN LOREDO
Corrections Issued 4/22/2021 COLIN LOREDO
Quality Review Completed 4/27/2021 OMID HEDAYAT
Applicant returned to address corrections 6/28/2022 COLIN LOREDO
Plan Check Approved 3/13/2023 RAPHAEL ROSAS
Issued 9/25/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/13/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/19/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 10/10/2021 RUEL COLE
Low Impact Development Cleared 6/21/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/4/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2023 Approved JOHN HAYES
Deputy Drilled-In Anchors 3/11/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/20/2024 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/27/2024 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/1/2024 Partial Approval ROBERT GOLD
Deputy Reinf. Concrete 4/3/2024 Conditional Approval JOHN HAYES
Footing/Foundation/Slab 4/10/2024 Not Ready for Inspection JOSE AVILA
Deputy Drilled-In Anchors 4/16/2024 Conditional Approval JOHN HAYES
Deputy Drilled-In Anchors 4/16/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 4/19/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 4/23/2024 Corrections Issued JOHN COLEMAN
Green Building Rough 4/23/2024 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 5/7/2024 Partial Approval JOHN HAYES
PLUMBING-Rough 5/7/2024 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 5/13/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/15/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Insulation 5/17/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/29/2024 Corrections Issued JOSE AVILA
Green Building Rough 5/29/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Corrections Issued JOSE AVILA
Deputy Wood Construction 7/12/2024 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 7/15/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Approved JOSE AVILA