7945 N LOUISE AVE 91325

Certificate Information: 7945 N LOUISE AVE 91325

Application / Permit
21014-20000-01084
Plan Check / Job No.
B21VN02663
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO (N) ACCESSORY DWELLING UNIT & ADD FOR (N) LIVING ROOM, KITCHEN & (2) BEDROOMS & (2) FULL BATHROOMS PER LAMC 12.22A33(c)(d)(g) & WFPP
Permit Issued
Issued on 9/14/2021
Issuing Office
Current Status
CofO Issued on 2/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 NILOOFAR MEHRAIN
Corrections Issued 3/20/2021 NILOOFAR MEHRAIN
Building Plans Picked Up 3/26/2021 APPLICANT
Plan Check Approved 8/25/2021 NILOOFAR MEHRAIN
Issued 9/14/2021 APPLICANT
CofO in Progress 2/7/2023 RAUL OLAGI
Permit Finaled 2/17/2023 MICHAEL SMITH
CofO Issued 2/17/2023 MICHAEL SMITH
Permit Finaled 2/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/9/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/9/2021 GUILLERMO PETRA
Permit Cleared 4/9/2021 GUILLERMO PETRA
Sewer availability Cleared 4/9/2021 GUILLERMO PETRA
Hydrant and Access approval Cleared 6/8/2021 ROBERT DUFF
Low Impact Development Cleared 8/13/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/14/2021 ABDULLAH SADOZAI

Contact Information

Contractor Carlos Anaya; Lic. No.: 1034169-B 6936 JUMILLA AVE      WINNETKA, CA 91306

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/16/2021 Partial Approval AMY COLIN
Deputy Drilled-In Anchors 9/30/2021 Approved JACK KARGODORIAN
Footing/Foundation/Slab 10/4/2021 Corrections Issued JACK KARGODORIAN
Deputy Drilled-In Anchors 10/6/2021 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 10/6/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 11/22/2021 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 12/20/2021 Corrections Issued RAUL OLAGI
PLUMBING-Rough 12/20/2021 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 12/27/2021 Not Ready for Inspection ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Partial Approval ALAN MORELOS
HVAC-Rough 12/27/2021 Not Ready for Inspection ALAN MORELOS
PLUMBING-Rough 12/27/2021 Approved ALAN MORELOS
ELECTRICAL-Rough 1/13/2022 Approved RAUL OLAGI
HVAC-Rough 1/13/2022 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 1/13/2022 Corrections Issued RAUL OLAGI
HVAC-Rough 1/20/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 1/20/2022 Partial Approval RAUL OLAGI
Insulation 1/27/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 1/27/2022 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 2/1/2022 Partial Approval RAUL OLAGI
Drywall Nailing 2/14/2022 Approved ALAN MORELOS
Shower Pan 2/14/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 4/26/2022 Approved RAUL OLAGI
ELECTRICAL-Final 4/26/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 4/26/2022 Approved RAUL OLAGI
Green Building Final 4/26/2022 Approved RAUL OLAGI
Green Building Rough 4/26/2022 Approved RAUL OLAGI
HVAC-Final 4/26/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/26/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Final 5/4/2022 Approved RAUL OLAGI
Final 5/4/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 5/4/2022 Approved RAUL OLAGI
Smoke Detectors 5/4/2022 Approved RAUL OLAGI
Final 2/7/2023 OK to Issue CofO RAUL OLAGI