4420 N ARCOLA AVE 91602
Certificate Information: 4420 N ARCOLA AVE 91602
- Application / Permit
- 21014-20000-01058
- Plan Check / Job No.
- B21VN02607
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 3' x 11' TO ENLARGE THE (E) CLOSET IN THE MASTER BEDROOM.
- Permit Issued
- Issued on 4/7/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2021 | LUIS RINCON |
| Corrections Issued | 3/9/2021 | LUIS RINCON |
| Corrections Issued | 3/10/2021 | LUIS RINCON |
| Corrections Issued | 3/11/2021 | LUIS RINCON |
| Plan Check Approved | 4/6/2021 | LUIS RINCON |
| Issued | 4/7/2021 | APPLICANT |
| Building Plans Picked Up | 4/9/2021 | APPLICANT |
| CofO in Progress | 2/16/2022 | THOMAS FINNILA |
| CofO Issued | 5/4/2022 | MICHAEL SMITH |
| Permit Finaled | 5/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/25/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2021 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 5/10/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 5/13/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/27/2021 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/27/2021 | Corrections Issued | THOMAS FINNILA |
| Insulation | 5/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/9/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/9/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 6/9/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 6/9/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 6/15/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/15/2021 | Approved | MORRIS JACKSON |
| Final | 12/13/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 12/13/2021 | Approved | THOMAS FINNILA |
| MERV13>=Final | 12/13/2021 | Approved | THOMAS FINNILA |
| Smoke Detectors | 12/13/2021 | Corrections Issued | THOMAS FINNILA |
| Final | 12/30/2021 | Partial Inspection | THOMAS FINNILA |
| Smoke Detectors | 12/30/2021 | Approved | THOMAS FINNILA |
| Final | 2/15/2022 | OK to Issue CofO | THOMAS FINNILA |