3296 S INGLEWOOD BLVD 90066

Certificate Information: 3296 S INGLEWOOD BLVD 90066

Application / Permit
21014-20000-01046
Plan Check / Job No.
B21VN02582
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 SELLA BENYAMIN
Corrections Issued 3/26/2021 SELLA BENYAMIN
Quality Review Completed 4/19/2021 STEVEN KIM
Plan Check Approved 9/28/2021 SELLA BENYAMIN
Issued 10/12/2021 APPLICANT
Permit Finaled 8/26/2025 CLAUDIO MORENO
CofO Issued 8/26/2025 CLAUDIO MORENO
Permit Finaled 8/26/2025 CLAUDIO MORENO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/3/2021 TRACY TATE
Sewer availability Cleared 5/3/2021 TRACY TATE
Low Impact Development Cleared 7/30/2021 TA ANH
Roof/Waste drainage to street Cleared 8/17/2021 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 9/28/2021 SELLA BENYAMIN
Grading Pre-Inspection Cleared 9/28/2021 SELLA BENYAMIN

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: C24587 21243 VENTURA BLVD #115      WOODLAND HILLS, CA 91364
Contractor Baker Mick Construction Inc; Lic. No.: 970371-B 17535 BULLOCK STREET      ENCINO, CA 91316

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/7/2022 Partial Approval MARIAN PODPORA
Underground Mechanical 3/7/2022 Partial Approval MARIAN PODPORA
Deputy Reinf. Concrete 3/16/2022 Approved MARIAN PODPORA
Wood Frame 3/22/2022 Partial Approval MARIAN PODPORA
Insulation 3/25/2022 Partial Approval MARIAN PODPORA
Excavation/Setback/Form/Re-Bar 4/1/2022 Approved MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Not Ready for Inspection JOHN MATTILLO
Wood Frame 4/13/2022 Not Ready for Inspection JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Partial Approval JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Partial Approval MARIAN PODPORA
BUILDING-Rough-Frame 7/11/2022 Corrections Issued JOHN MATTILLO
Green Building Rough 7/11/2022 Approved JOHN MATTILLO
Rough-Elec/Plmb/HVAC 7/11/2022 Approved JOHN MATTILLO
Deputy Drilled-In Anchors 8/18/2022 Conditional Approval JOHN MATTILLO
Excavation/Setback/Form/Re-Bar 8/18/2022 Approved JOHN MATTILLO
Deputy Drilled-In Anchors 9/1/2022 Approved MARIAN PODPORA
BUILDING-Rough-Frame 10/18/2022 Approved MARIAN PODPORA
Interior/Exterior Lathing 10/27/2022 Approved RYAN BARNES
Insulation 10/31/2022 Approved RYAN BARNES
Drywall Nailing 11/7/2022 Approved JOHN MATTILLO
Interior/Exterior Lathing 11/18/2022 Partial Approval MARIAN PODPORA
Shower Pan 11/18/2022 Approved MARIAN PODPORA
Wood Frame 3/28/2023 Partial Approval RYAN BARNES
Deck 5/18/2023 Not Ready for Inspection ANDREW BEELI
Deputy Steel/Welding 6/13/2023 Partial Approval ANDREW BEELI
Final 10/5/2023 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 10/5/2023 Approved ANDREW BEELI
Green Building Final 10/5/2023 Corrections Issued ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV No Gas ANDREW BEELI
Smoke Detectors 10/5/2023 Approved ANDREW BEELI
Final 10/26/2023 Partial Approval ANDREW BEELI
Green Building Final 10/26/2023 Approved ANDREW BEELI
Final 7/8/2025 Partial Approval ANDREW BEELI
Interior/Exterior Lathing 7/9/2025 Approved ANDREW BEELI
SWPPP-Const. Storm Water 7/9/2025 Completed ANDREW BEELI