CONVERT 18'-4" X 20'-2" (E) ATTACHED GARAGE INTO A (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ENCLOSE 5' X 12'-4" PORCH TO ENLARGE LIVING ROOM, ADD 4' X 12'-4" & 17' X 17'-1" IRREGULAR SHAPE ADDITIONS TO SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 RAPHAEL ROSAS
Corrections Issued 3/18/2021 RAPHAEL ROSAS
Issued 5/12/2021 APPLICANT
Building Plans Picked Up 5/13/2021 APPLICANT
CofO in Progress 10/21/2021 WILLIAM KUEHN
CofO Issued 12/17/2021 MICHAEL SMITH
Permit Finaled 12/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/22/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/22/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/22/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/22/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/22/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/22/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 5/12/2021 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos M; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/16/2021 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 6/17/2021 Approved JOHN HAYES
Footing/Foundation/Slab 6/17/2021 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Partial Approval MATTHEW NELSON
PLUMBING-Rough 7/1/2021 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 8/10/2021 Approved WILLIAM KUEHN
ELECTRICAL-Rough 8/10/2021 Approved WILLIAM KUEHN
Green Building Rough 8/10/2021 Not Ready for Inspection WILLIAM KUEHN
HVAC-Rough 8/10/2021 Approved WILLIAM KUEHN
MERV13>=Rough 8/10/2021 Approved WILLIAM KUEHN
PLUMBING-Rough 8/10/2021 Approved WILLIAM KUEHN
Wood Frame 8/10/2021 Partial Approval WILLIAM KUEHN
Insulation 8/20/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 8/20/2021 Partial Inspection WILLIAM KUEHN
Drywall Nailing 8/31/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 8/31/2021 Partial Inspection WILLIAM KUEHN
Shower Pan 8/31/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 10/18/2021 Approved WILLIAM KUEHN
Final 10/18/2021 Corrections Issued WILLIAM KUEHN
Final 10/18/2021 Not Ready for Inspection WILLIAM KUEHN
Green Building Final 10/18/2021 Approved WILLIAM KUEHN
Green Building Rough 10/18/2021 Approved WILLIAM KUEHN
MERV13>=Final 10/18/2021 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 10/18/2021 Approved WILLIAM KUEHN
Final 10/20/2021 OK to Issue CofO WILLIAM KUEHN