1711 S KINGSLEY DR 90006

Certificate Information: 1711 S KINGSLEY DR 90006

Application / Permit
21014-20000-01044
Plan Check / Job No.
B21VN02577
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2' X 12'-1" ADDITION TO ENLARGE KITCHEN, 14'-9" X 13'-7" DECK ADDITION, AND REMODEL THROUGHOUT SINGLE FAMILY DWELLING. CONVERT SITTING ROOM TO NEW BEDROOM. REMOVE AND REPLACE DOORS AND WINDOWS THROUGHOUT.
Permit Issued
Issued on 5/10/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 JEROME MAGAT PALMA
Corrections Issued 3/20/2021 JEROME MAGAT PALMA
Plan Check Approved 4/21/2021 JEROME MAGAT PALMA
Building Plans Picked Up 4/22/2021 APPLICANT
Issued 5/10/2021 APPLICANT
CofO in Progress 2/24/2022 KATHRYN BUTTERWORTH
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/5/2021 CELINA MORENO
Sewer availability Cleared 4/5/2021 CELINA MORENO
HPOZ Cleared 4/6/2021 DEEPEAKA DHALIWAL
Eng Process Fee Ord 176,300 Cleared 4/13/2021 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/20/2021 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/20/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 9/1/2021 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Partial Approval KATHRYN BUTTERWORTH
HVAC-Rough 9/1/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 9/1/2021 Corrections Issued KATHRYN BUTTERWORTH
Wood Frame 9/1/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/7/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 9/7/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 9/7/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 9/7/2021 Approved KATHRYN BUTTERWORTH
Shower Pan 9/7/2021 Approved KATHRYN BUTTERWORTH
Insulation 9/9/2021 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 9/9/2021 Approved WILLIAM WREN
Insulation 9/13/2021 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 9/17/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/22/2021 Partial Approval KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/27/2021 Approved OSVALDO PARAMO
ELECTRICAL-Final 1/28/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 1/28/2022 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 1/28/2022 Approved KATHRYN BUTTERWORTH
HVAC-Final 1/28/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 1/28/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 1/28/2022 Approved KATHRYN BUTTERWORTH
Final 2/9/2022 Corrections Issued KATHRYN BUTTERWORTH
Sewer 2/14/2022 Approved KATHRYN BUTTERWORTH
Final 2/22/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 2/24/2022 OK to Issue CofO KATHRYN BUTTERWORTH