1711 S KINGSLEY DR 90006
Certificate Information: 1711 S KINGSLEY DR 90006
- Application / Permit
- 21014-20000-01044
- Plan Check / Job No.
- B21VN02577
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2' X 12'-1" ADDITION TO ENLARGE KITCHEN, 14'-9" X 13'-7" DECK ADDITION, AND REMODEL THROUGHOUT SINGLE FAMILY DWELLING. CONVERT SITTING ROOM TO NEW BEDROOM. REMOVE AND REPLACE DOORS AND WINDOWS THROUGHOUT.
- Permit Issued
- Issued on 5/10/2021
- Issuing Office
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 3/20/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 4/21/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/22/2021 | APPLICANT |
| Issued | 5/10/2021 | APPLICANT |
| CofO in Progress | 2/24/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
| CofO Issued | 3/11/2022 | DEROLD HAUFF |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/5/2021 | CELINA MORENO |
| Sewer availability | Cleared | 4/5/2021 | CELINA MORENO |
| HPOZ | Cleared | 4/6/2021 | DEEPEAKA DHALIWAL |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/20/2021 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/20/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 9/1/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Rough | 9/1/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 9/1/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Wood Frame | 9/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/7/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 9/7/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 9/7/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 9/7/2021 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 9/7/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 9/9/2021 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 9/9/2021 | Approved | WILLIAM WREN |
| Insulation | 9/13/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 9/17/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 9/22/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 9/27/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 1/28/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 1/28/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 1/28/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 1/28/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 1/28/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 1/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 2/9/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Sewer | 2/14/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 2/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 2/24/2022 | OK to Issue CofO | KATHRYN BUTTERWORTH |