781 N RANCH LANE 90272
Certificate Information: 781 N RANCH LANE 90272
- Application / Permit
- 21014-20000-01022
- Plan Check / Job No.
- B21VN02547
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 46'9-3/4"X5'6" 1ST FLOOR ADDITION, 7'6"X20'2" BALCONY ENCLOSURE ADDITION, 1'2"X9'6" (N) JULIET BALCONY & REMODEL TO (E) SFD
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 9/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | MARVEL DELACRUZ |
| Corrections Issued | 4/8/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 4/15/2021 | STEVEN KIM |
| Plan Check Approved | 7/19/2021 | MARVEL DELACRUZ |
| Issued | 7/19/2021 | APPLICANT |
| CofO in Progress | 8/18/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 9/12/2023 | DANIEL ORRANTE |
| CofO Issued | 9/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 5/21/2021 | NIKTA MOUSAVI |
| Distance to fire station | Cleared | 6/27/2021 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 6/27/2021 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 7/6/2021 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 7/19/2021 | MARVEL DELACRUZ |
| Green Code | Cleared | 7/19/2021 | MARVEL DELACRUZ |
Contact Information
| Architect | Williams,, Noel C; Lic. No.: C33223 | 810 SOUTH FLOWER STREET UNIT 213 LOS ANGELES, CA 90017 |
| Contractor | Harris-Anderson; Lic. No.: 857280-B | 11150 SANTA MONICA BLVD SUITE 600 LOS ANGELES, CA 90025 |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/20/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/27/2021 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/2/2021 | Partial Approval | JOHN KIDWELL |
| Special/Order Compliance | 11/2/2021 | Corrections Issued | JOHN KIDWELL |
| Deputy Wood Construction | 3/22/2022 | Approved | MICHAEL PELHAM |
| Sewer | 5/12/2022 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 5/20/2022 | Conditional Approval | MICHAEL PELHAM |
| Green Building Rough | 5/23/2022 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 5/23/2022 | Approved | JOHN KIDWELL |
| Pre-Inspection | 6/10/2022 | Partial Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/14/2022 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 6/14/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/24/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 6/24/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/20/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/1/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/5/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/15/2022 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/15/2022 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 9/6/2022 | Conditional Approval | JOHN KIDWELL |
| Drywall Nailing | 9/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 9/22/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 9/29/2022 | Approved | KEVIN SARGSYAN |
| Final | 9/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/4/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/26/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 7/5/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 7/5/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/2/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 8/2/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/7/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 8/7/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/7/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 8/7/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/7/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 8/7/2023 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/7/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 8/17/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |