6709 N YARMOUTH AVE 91335
Certificate Information: 6709 N YARMOUTH AVE 91335
- Application / Permit
- 21014-20000-01021
- Plan Check / Job No.
- B21VN02545
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 8'-5" X 16'-5" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A. 33(c) and (d)
- Permit Issued
- Issued on 6/17/2021
- Issuing Office
- Current Status
- CofO Corrected on 9/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 3/20/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 6/17/2021 | JEROME MAGAT PALMA |
| Issued | 6/17/2021 | APPLICANT |
| Building Plans Picked Up | 6/17/2021 | APPLICANT |
| CofO in Progress | 9/23/2021 | VINCENT HANLEY |
| Re-Activate Permit | 9/24/2021 | JOHN JANSON |
| CofO Issued-Status Void | 9/24/2021 | JOHN JANSON |
| Permit Finaled-Status Void | 9/24/2021 | JOHN JANSON |
| Permit Finaled | 9/24/2021 | JOHN JANSON |
| CofO Corrected | 9/24/2021 | JOHN JANSON |
| Permit Finaled | 9/24/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/31/2021 | GABRIEL ROBLES |
| ZI | Cleared | 4/6/2021 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 6/9/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Neo Builders Inc; Lic. No.: 1061134-B | 6238 ALCOVE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/7/2021 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/8/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/8/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 7/8/2021 | Approved | VINCENT HANLEY |
| Underground Mechanical | 7/8/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/30/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/30/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/30/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 7/30/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/30/2021 | Approved | VINCENT HANLEY |
| Insulation | 8/4/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/4/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 8/4/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/5/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/5/2021 | Approved | VINCENT HANLEY |
| Insulation | 8/5/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/5/2021 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 8/9/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/9/2021 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 9/23/2021 | Approved | VINCENT HANLEY |
| Final | 9/23/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 9/23/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 9/23/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/23/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/23/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/23/2021 | Approved | VINCENT HANLEY |