20554 W QUEDO DR 91364
Certificate Information: 20554 W QUEDO DR 91364
- Application / Permit
- 21014-20000-01019
- Plan Check / Job No.
- B21VN02544
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO (E) REAR PATIO COVER, ADD (N) FAMILY ROOM, 1/2 BATH, LAUNDRY ROOM & WALK IN CLOSET (36'-10" X 15'-9"), EXPAND (E) ENTRY & ADD (N) FRONT PATIO COVER (4'-7" X 10'-10"); CHANGE ROOF FRAMING OVER KITCHEN/DINING RM TO VAULTED CEILING
- Permit Issued
- Issued on 2/18/2022
- Issuing Office
- Current Status
- Issued on 2/18/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/12/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 4/19/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 12/21/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 1/25/2022 | NILOOFAR MEHRAIN |
| Issued | 2/18/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 9/24/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 9/24/2021 | NILOOFAR MEHRAIN |
| Hydrant and Access approval | Cleared | 10/1/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/3/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 2919 BURBANK BLVD STE D BURBANK, CA 91505 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 7/1/2022 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 8/22/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Corrections Issued | PETER FOLLING |
| HVAC-Rough | 8/22/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 8/22/2022 | Approved | PETER FOLLING |
| Underground Mechanical | 8/22/2022 | Partial Approval | PETER FOLLING |
| HVAC-Rough | 8/31/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 9/14/2022 | Corrections Issued | PETER FOLLING |
| Green Building Rough | 9/14/2022 | Not Ready for Inspection | PETER FOLLING |
| Interior/Exterior Lathing | 9/14/2022 | Partial Approval | PETER FOLLING |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 9/21/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 9/28/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 2/17/2023 | Approved | SEAN WIRCH |
| HVAC-Final | 2/17/2023 | Approved | SEAN WIRCH |
| PLUMBING-Final | 2/17/2023 | Approved | SEAN WIRCH |
| Final | 7/30/2025 | Corrections Issued | JOHN HAYES |
| Green Building Final | 7/30/2025 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 7/30/2025 | Approved | JOHN HAYES |