1623 S REEVES ST 90035

Certificate Information: 1623 S REEVES ST 90035

Application / Permit
21014-20000-01016
Plan Check / Job No.
B21VN02539
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION OF (3) BEDROOMS, (2) FULL BATHROOMS & LAUNDRY ROOM (IRR 41'-7" X 29'-3") TO (E) 1-STORY SFD; INTERIOR REMODEL TO 1ST FLOOR
Permit Issued
Issued on 9/30/2021
Issuing Office
Current Status
CofO Issued on 10/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 NILOOFAR MEHRAIN
Corrections Issued 3/27/2021 NILOOFAR MEHRAIN
Quality Review Completed 3/30/2021 CHON CHIO KUO
Applicant returned to address corrections 9/2/2021 NILOOFAR MEHRAIN
Plan Check Approved 9/7/2021 NILOOFAR MEHRAIN
Issued 9/30/2021 APPLICANT
CofO in Progress 10/7/2022 OGANES TARAKHCHYAN
Permit Finaled 10/17/2022 DANIEL ORRANTE
CofO Issued 10/17/2022 DANIEL ORRANTE
Permit Finaled 10/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 8/13/2021 JOHN CONNEALLY
Low Impact Development Cleared 8/13/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/17/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/20/2021 DINAH GARIN
Sewer availability Cleared 8/20/2021 DINAH GARIN
GPI Written Notices Cleared 9/1/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 9/1/2021 NILOOFAR MEHRAIN

Contact Information

Contractor A R M Builders Inc; Lic. No.: 915352-B 1080 S LA CIENEGA #311      LOS ANGELES, CA 90035
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/30/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 11/30/2021 Approved KEVIN SARGSYAN
METHANE-Subgrade 11/30/2021 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/2/2021 Approved KEVIN SARGSYAN
Wood Frame 12/13/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 3/23/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 3/23/2022 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval EVAN COOPER
Green Building Rough 3/23/2022 Not Ready for Inspection EVAN COOPER
HVAC-Rough 3/23/2022 Corrections Issued EVAN COOPER
METHANE-Rough 3/23/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 4/11/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 4/11/2022 Corrections Issued KEVIN SARGSYAN
Green Building Rough 4/11/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 4/11/2022 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 4/11/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 4/11/2022 Corrections Issued KEVIN SARGSYAN
Wood Frame 4/11/2022 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 4/21/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 4/21/2022 Approved EVAN COOPER
Green Building Rough 4/21/2022 Approved EVAN COOPER
HVAC-Rough 4/21/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 4/21/2022 Partial Approval EVAN COOPER
Rough-Elec/Plmb/HVAC 4/21/2022 Partial Approval EVAN COOPER
Insulation 5/9/2022 No Access for Inspection KEVIN SARGSYAN
Shower Pan 5/9/2022 No Access for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 5/11/2022 Conditional Approval EVAN COOPER
Green Building Rough 5/11/2022 Approved EVAN COOPER
Insulation 5/11/2022 Approved EVAN COOPER
Interior/Exterior Lathing 5/11/2022 Approved EVAN COOPER
Shower Pan 5/11/2022 Approved EVAN COOPER
Interior/Exterior Lathing 5/16/2022 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 5/20/2022 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 5/20/2022 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 5/25/2022 Approved KEVIN SARGSYAN
Shower Pan 5/25/2022 Approved KEVIN SARGSYAN
Drywall Nailing 6/1/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 9/9/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/9/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Not Ready OGANES TARAKHCHYAN
ELECTRICAL-Final 9/15/2022 Approved ANDREW NAVE
PLUMBING-Final 9/15/2022 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 9/19/2022 Approved ANDREW NAVE
Final 9/19/2022 Corrections Issued ANDREW NAVE
Green Building Final 9/19/2022 Corrections Issued ANDREW NAVE
HVAC-Final 9/19/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 9/19/2022 Approved ANDREW NAVE
Green Building Final 9/22/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 9/22/2022 Approved OGANES TARAKHCHYAN
Final 10/6/2022 OK to Issue CofO OGANES TARAKHCHYAN