18039 W ROSITA ST 91316
Certificate Information: 18039 W ROSITA ST 91316
- Application / Permit
- 21014-20000-00992
- Plan Check / Job No.
- B21VN02456
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY AND TWO STORY ADDITIONS TO EXISTING SINGLE FAMILY DWELLING; NEW ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | SELLA BENYAMIN |
| Corrections Issued | 3/22/2021 | SELLA BENYAMIN |
| Quality Review Completed | 3/24/2021 | STEVEN KIM |
| Applicant returned to address corrections | 7/27/2021 | SELLA BENYAMIN |
| Plan Check Approved | 8/31/2021 | SELLA BENYAMIN |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 9/26/2023 | PETER FOLLING |
| CofO Issued | 8/27/2024 | JOHN JANSON |
| Permit Finaled | 8/27/2024 | JOHN JANSON |
Permit Application Clearance Information
| Permit | Cleared | 4/5/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/6/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 5/21/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 7/8/2021 | JOHN KIM |
| Low Impact Development | Cleared | 7/16/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/19/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/7/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/7/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 10/25/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/25/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 11/1/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 1/10/2022 | Corrections Issued | DAVID SANDOVAL |
| Wood Frame | 1/10/2022 | Partial Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 1/13/2022 | Partial Approval | DAVID SANDOVAL |
| Wood Frame | 1/13/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/21/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Rough | 3/21/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 3/21/2022 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2022 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Rough | 3/23/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 3/29/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/17/2022 | No Access for Inspection | DAVID SANDOVAL |
| Wood Frame | 5/17/2022 | No Access for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/23/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 5/23/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 6/16/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 6/16/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Shower Pan | 6/16/2022 | Approved | DAVID SANDOVAL |
| Insulation | 6/22/2022 | Corrections Issued | DAVID SANDOVAL |
| Interior/Exterior Lathing | 6/22/2022 | Partial Approval | DAVID SANDOVAL |
| Shower Pan | 6/22/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 8/1/2022 | Approved | DAVID SANDOVAL |
| Insulation | 8/1/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 2/3/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/16/2023 | Approved | JOHN KIDWELL |
| Final | 6/16/2023 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 6/16/2023 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 6/16/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 9/25/2023 | Approved | PETER FOLLING |
| Final | 9/25/2023 | OK to Issue CofO | PETER FOLLING |
| Green Building Final | 9/25/2023 | Approved | PETER FOLLING |
| HVAC-Final | 9/25/2023 | Approved | PETER FOLLING |
| PLUMBING-Final | 9/25/2023 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 9/25/2023 | Approved | PETER FOLLING |
| Special/Order Compliance | 10/27/2023 | Corrections Issued | SEAN HAUPT |