18039 W ROSITA ST 91316

Certificate Information: 18039 W ROSITA ST 91316

Application / Permit
21014-20000-00992
Plan Check / Job No.
B21VN02456
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY AND TWO STORY ADDITIONS TO EXISTING SINGLE FAMILY DWELLING; NEW ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/30/2021
Issuing Office
Current Status
CofO Issued on 8/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 SELLA BENYAMIN
Corrections Issued 3/22/2021 SELLA BENYAMIN
Quality Review Completed 3/24/2021 STEVEN KIM
Applicant returned to address corrections 7/27/2021 SELLA BENYAMIN
Plan Check Approved 8/31/2021 SELLA BENYAMIN
Issued 9/30/2021 APPLICANT
CofO in Progress 9/26/2023 PETER FOLLING
CofO Issued 8/27/2024 JOHN JANSON
Permit Finaled 8/27/2024 JOHN JANSON

Permit Application Clearance Information

Permit Cleared 4/5/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/6/2021 ADRIAN CASTRO
Sewer availability Cleared 4/6/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 5/21/2021 MATTHEW CRAIG
Trees in Parkway Cleared 7/8/2021 JOHN KIM
Low Impact Development Cleared 7/16/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/19/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/7/2021 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 10/7/2021 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 10/19/2021 Not Ready for Inspection DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 10/25/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 10/25/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 11/1/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 1/10/2022 Corrections Issued DAVID SANDOVAL
Wood Frame 1/10/2022 Partial Inspection DAVID SANDOVAL
PLUMBING-Rough 1/13/2022 Partial Approval DAVID SANDOVAL
Wood Frame 1/13/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 3/21/2022 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Corrections Issued DAVID SANDOVAL
HVAC-Rough 3/21/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 3/21/2022 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Corrections Issued DAVID SANDOVAL
HVAC-Rough 3/23/2022 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 3/29/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 5/17/2022 No Access for Inspection DAVID SANDOVAL
Wood Frame 5/17/2022 No Access for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 5/23/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Approved DAVID SANDOVAL
HVAC-Rough 5/23/2022 Approved DAVID SANDOVAL
Green Building Rough 6/16/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 6/16/2022 Not Ready for Inspection DAVID SANDOVAL
Shower Pan 6/16/2022 Approved DAVID SANDOVAL
Insulation 6/22/2022 Corrections Issued DAVID SANDOVAL
Interior/Exterior Lathing 6/22/2022 Partial Approval DAVID SANDOVAL
Shower Pan 6/22/2022 Approved DAVID SANDOVAL
Drywall Nailing 8/1/2022 Approved DAVID SANDOVAL
Insulation 8/1/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 8/1/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 2/3/2023 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 6/16/2023 Approved JOHN KIDWELL
Final 6/16/2023 Corrections Issued JOHN KIDWELL
Green Building Final 6/16/2023 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 6/16/2023 Approved JOHN KIDWELL
ELECTRICAL-Final 9/25/2023 Approved PETER FOLLING
Final 9/25/2023 OK to Issue CofO PETER FOLLING
Green Building Final 9/25/2023 Approved PETER FOLLING
HVAC-Final 9/25/2023 Approved PETER FOLLING
PLUMBING-Final 9/25/2023 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Approved PETER FOLLING
Service/Power Release 9/25/2023 Approved PETER FOLLING
Special/Order Compliance 10/27/2023 Corrections Issued SEAN HAUPT