10630 N ALDEA AVE 91344

Certificate Information: 10630 N ALDEA AVE 91344

Application / Permit
21014-20000-00989
Plan Check / Job No.
B21VN02449
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION ( 21'-6" X 16'-0" ) TO EX. SFD FOR NEW BEDROOM, BATHROOM AND CLOSET. WORK PER ENGINEER.
Permit Issued
Issued on 12/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 KAVIAN REFAHI
Corrections Issued 3/20/2021 KAVIAN REFAHI
Applicant returned to address corrections 6/12/2021 RICHARD GARCIA
Applicant returned to address corrections 10/19/2021 RICHARD GARCIA
Applicant returned to address corrections 4/9/2022 RICHARD GARCIA
Applicant returned to address corrections 8/16/2022 RICHARD GARCIA
Building Plans Picked Up 8/22/2022 APPLICANT
Applicant returned to address corrections 9/22/2022 RICHARD GARCIA
Plan Check Approved 12/20/2022 ROSENDO MEDINA
Issued 12/20/2022 APPLICANT
CofO in Progress 11/29/2023 JEFFREY HARTLINE
Permit Finaled 12/12/2023 JOHN JANSON
CofO Issued 12/12/2023 JOHN JANSON
Permit Finaled 12/12/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/26/2021 CARLOS AGUILERA
Sewer availability Cleared 8/26/2021 CARLOS AGUILERA
ZI Cleared 8/27/2021 TERRI OSBORNE
Low Impact Development Cleared 10/6/2021 TA ANH
Roof/Waste drainage to street Cleared 10/6/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Wubneh,, Amanuel Manaye; Lic. No.: C90142 1504 WEST PORTER AVE      VISALIA, CA 93291

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/21/2023 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 6/28/2023 Approved DAVID SCANTLIN
ELECTRICAL-Rough 8/2/2023 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 8/24/2023 Partial Approval JOHN KIDWELL
Green Building Rough 8/24/2023 Approved JOHN KIDWELL
Rough-Elec/Plmb/HVAC 8/24/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 9/6/2023 Approved DAVID SCANTLIN
Green Building Rough 9/6/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 9/6/2023 Partial Approval DAVID SCANTLIN
Shower Pan 9/6/2023 Approved DAVID SCANTLIN
Insulation 9/14/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 9/14/2023 Approved DAVID SCANTLIN
Drywall Nailing 9/18/2023 Approved DAVID SCANTLIN
Final 10/24/2023 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 10/24/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 10/24/2023 Not Ready for Inspection DAVID SCANTLIN
Special/Order Compliance 10/24/2023 Approved HORACE FULTZ
Final 11/17/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 11/17/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 11/17/2023 Approved DAVID SCANTLIN
Final 11/28/2023 OK to Issue CofO JEFFREY HARTLINE
Service/Power Release 11/28/2023 Approved JEFFREY HARTLINE