10139-10139 1/2 W STAGG ST 91352
Certificate Information: 10139-10139 1/2 W STAGG ST 91352
- Application / Permit
- 21014-20000-00975
- Plan Check / Job No.
- B21VN02410
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD AND CONVERT ATTACHED GARAGE WITH ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) FIRE SPRINKLER NFPA-13D
- Permit Issued
- Issued on 1/5/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/2/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 5/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 5/21/2021 | APPLICANT |
| Plan Check Approved | 1/3/2022 | MOHAMMAD ESMAILI |
| Issued | 1/5/2022 | APPLICANT |
| CofO in Progress | 10/26/2022 | DAVID ANDERSON |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/4/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 10/13/2021 | MARCO SANCHEZ |
| Hydrant and Access approval | Cleared | 11/29/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/18/2022 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 5/20/2022 | Conditional Approval | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Approved | MATT KELLERMAN |
| Footing/Foundation/Slab | 5/23/2022 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 6/13/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Insulation | 6/13/2022 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 6/13/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 6/13/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 6/13/2022 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/15/2022 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 6/15/2022 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 6/15/2022 | Approved | DAVID ANDERSON |
| Insulation | 6/16/2022 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 7/18/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/19/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/19/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 7/19/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | DAVID ANDERSON |
| Wood Frame | 7/20/2022 | Approved | DAVID ANDERSON |
| Insulation | 7/25/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/27/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/29/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/12/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 8/16/2022 | Approved | DAVID ANDERSON |
| Sewer | 9/8/2022 | Approved | DAVID ANDERSON |
| Underground Mechanical | 9/8/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 9/21/2022 | Approved | DAVID ANDERSON |
| Final | 9/21/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 9/21/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 9/21/2022 | Approved | DAVID ANDERSON |
| HVAC-Final | 9/21/2022 | Approved | DAVID ANDERSON |
| MERV13>=Final | 9/21/2022 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 9/21/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 9/21/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Not Required | DAVID ANDERSON |
| Smoke Detectors | 9/21/2022 | Approved | DAVID ANDERSON |
| Final | 10/25/2022 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 10/25/2022 | Approved | DAVID ANDERSON |