13557 W HARTLAND ST 91405

Certificate Information: 13557 W HARTLAND ST 91405

Application / Permit
21014-20000-00956
Plan Check / Job No.
B21VN02390
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL (E) SFD. PER ENGINEERING DESIGN.
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 10/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 ALFREDO JARA
Corrections Issued 3/23/2021 ALFREDO JARA
Applicant returned to address corrections 6/28/2021 LUISANGEL VALENZUELA
Issued 7/1/2021 APPLICANT
Building Plans Picked Up 7/1/2021 APPLICANT
CofO in Progress 9/28/2022 RAFAEL CORTES
Permit Finaled 10/12/2022 MICHAEL SMITH
CofO Issued 10/12/2022 MICHAEL SMITH
Permit Finaled 10/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 3/24/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/15/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/17/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/7/2021 Corrections Issued BRYAN MEYER
Underground Mechanical 7/7/2021 Not Ready for Inspection BRYAN MEYER
Deputy Drilled-In Anchors 7/9/2021 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 7/16/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/9/2021 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 8/9/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/13/2021 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 9/3/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 9/3/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 9/3/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 9/16/2021 Approved WILLIAM KUEHN
PLUMBING-Rough 9/22/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 9/24/2021 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/18/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/18/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 10/18/2021 Partial Approval CHRISTOPHE COCHRAN
Insulation 10/20/2021 Approved ASHLEY THOMPSON
Drywall Nailing 10/25/2021 Approved CHRISTOPHE COCHRAN
Shower Pan 10/28/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/2/2021 Partial Approval ARAM AVEDISIAN
Special/Order Compliance 6/27/2022 Corrections Issued MATT KELLERMAN
Final 7/20/2022 Corrections Issued RAFAEL CORTES
Green Building Final 7/20/2022 Partial Approval RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 7/20/2022 Not Ready for Inspection RAFAEL CORTES
Final 8/24/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Final 8/24/2022 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 8/24/2022 Not Ready for Inspection RAFAEL CORTES
Final 9/7/2022 Corrections Issued RAFAEL CORTES
Green Building Final 9/7/2022 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved RAFAEL CORTES
Smoke Detectors 9/7/2022 Approved RAFAEL CORTES
Final 9/27/2022 OK to Issue CofO RAFAEL CORTES