7512 N MILWOOD AVE 91303

Certificate Information: 7512 N MILWOOD AVE 91303

Application / Permit
21014-20000-00954
Plan Check / Job No.
B21VN02385
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19'6" X 17' ADDITION TO THE REAR OF THE (E) SFD. ALL WORK PER ENGINEER.
Permit Issued
Issued on 7/3/2021
Issuing Office
Current Status
CofO Issued on 12/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 KAVIAN REFAHI
Corrections Issued 3/9/2021 KAVIAN REFAHI
Applicant returned to address corrections 4/19/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 6/3/2021 PINANK PATEL
Plan Check Approved 6/16/2021 PINANK PATEL
Building Plans Picked Up 6/22/2021 APPLICANT
Issued 7/3/2021 APPLICANT
CofO in Progress 12/7/2021 STEVEN BACK
Permit Finaled 12/13/2021 JOHN JANSON
CofO Issued 12/13/2021 JOHN JANSON
Permit Finaled 12/13/2021 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/26/2021 LEE GUILBEAUX
Sewer availability Cleared 3/26/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/5/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/15/2021 Approved HENRY KIM
Excavation/Setback/Form/Re-Bar 7/15/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 7/15/2021 Corrections Issued HENRY KIM
Piling/Pier/Caisson 7/15/2021 Approved HENRY KIM
Pre-Inspection 7/15/2021 Corrections Issued HENRY KIM
Excavation/Setback/Form/Re-Bar 8/2/2021 Approved HENRY KIM
Footing/Foundation/Slab 8/2/2021 Approved HENRY KIM
Piling/Pier/Caisson 8/2/2021 Approved HENRY KIM
Pre-Inspection 8/2/2021 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Partial Approval HENRY KIM
Insulation 8/23/2021 Partial Approval HENRY KIM
BUILDING-Rough-Frame 9/15/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 9/15/2021 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 9/15/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 9/29/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 9/29/2021 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Corrections Issued HENRY KIM
Green Building Rough 9/29/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 9/29/2021 Approved HENRY KIM
BUILDING-Rough-Frame 10/8/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Approved HENRY KIM
Green Building Rough 10/8/2021 Approved HENRY KIM
Insulation 10/8/2021 Approved HENRY KIM
Interior/Exterior Lathing 10/8/2021 Approved HENRY KIM
Drywall Nailing 10/21/2021 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/7/2021 Approved STEVEN BACK
Final 12/7/2021 OK to Issue CofO STEVEN BACK
Green Building Final 12/7/2021 Approved STEVEN BACK
HVAC-Final 12/7/2021 Approved STEVEN BACK
PLUMBING-Final 12/7/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 12/7/2021 Approved STEVEN BACK