6655 N TEESDALE AVE 91606

Certificate Information: 6655 N TEESDALE AVE 91606

Application / Permit
21014-20000-00946
Plan Check / Job No.
B21VN02375
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 17'-4" X 24'-6" ADDITION TO (E) SFD FOR (N) LIVING ROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
CofO Issued on 2/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 RAPHAEL ROSAS
Corrections Issued 3/6/2021 RAPHAEL ROSAS
Applicant returned to address corrections 5/4/2021 RAPHAEL ROSAS
Issued 5/12/2021 APPLICANT
Building Plans Picked Up 5/14/2021 APPLICANT
CofO in Progress 11/2/2021 CHRISTOPHE COCHRAN
Permit Finaled 2/23/2022 MICHAEL SMITH
CofO Issued 2/23/2022 MICHAEL SMITH
Permit Finaled 2/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 5/6/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/22/2021 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 6/24/2021 Approved RICHARD DOCKUS
Footing/Foundation/Slab 6/24/2021 Approved RICHARD DOCKUS
Insulation 7/7/2021 Approved ALAN MORELOS
PLUMBING-Rough 7/7/2021 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 7/22/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 7/30/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/30/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 7/30/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/30/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/6/2021 Approved CHRISTOPHE COCHRAN
HVAC-Rough 8/6/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/6/2021 Partial Approval CHRISTOPHE COCHRAN
Insulation 8/10/2021 Approved AMY COLIN
Drywall Nailing 8/13/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/17/2021 Approved JOHN HAYES
Shower Pan 8/17/2021 Approved JOHN HAYES
Final 9/15/2021 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 9/15/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 9/15/2021 Approved CHRISTOPHE COCHRAN
Final 10/6/2021 Corrections Issued CHRISTOPHE COCHRAN
Final 10/28/2021 No Access for Inspection CHRISTOPHE COCHRAN
Final 11/2/2021 OK to Issue CofO CHRISTOPHE COCHRAN