5509 N WOODMAN AVE 91401

Certificate Information: 5509 N WOODMAN AVE 91401

Application / Permit
21014-20000-00933
Plan Check / Job No.
B21VN02363
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
25' X 17'-1" ADDITION AND 4'-4" X 15' ADDITION TO RELOCATE BEDROOM, ADD TWO BATHROOMS, REMODEL KITCHEN, AND ENLARGE LIVING ROOM / DINING ROOM.
Permit Issued
Issued on 5/3/2021
Issuing Office
Current Status
CofO Issued on 11/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 JEROME MAGAT PALMA
Corrections Issued 3/14/2021 JEROME MAGAT PALMA
Plan Check Approved 5/3/2021 JEROME MAGAT PALMA
Issued 5/3/2021 APPLICANT
Building Plans Picked Up 5/4/2021 APPLICANT
CofO in Progress 11/5/2021 JENNIFER RABUCHIN
CofO Issued 11/13/2021 MICHAEL SMITH
Permit Finaled 11/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/21/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 4/21/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/5/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 5/11/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/18/2021 Partial Approval JENNIFER RABUCHIN
Insulation 5/18/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Partial Approval KIM BEAUCHAMP
BUILDING-Rough-Frame 6/8/2021 Corrections Issued CHARLES POWELL
ELECTRICAL-Rough 6/8/2021 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Partial Approval CHARLES POWELL
Green Building Rough 6/8/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 6/8/2021 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Approved JENNIFER RABUCHIN
Green Building Rough 6/14/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/14/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/14/2021 Approved JENNIFER RABUCHIN
Special/Order Compliance 6/14/2021 Corrections Issued JENNIFER RABUCHIN
Insulation 6/17/2021 Approved TROY SANDERS
Drywall Nailing 6/25/2021 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/2/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/2/2021 Approved JENNIFER RABUCHIN
Final 11/2/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 11/2/2021 Approved JENNIFER RABUCHIN
HVAC-Final 11/2/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/2/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/2/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 11/2/2021 Approved JENNIFER RABUCHIN