5509 N WOODMAN AVE 91401
Certificate Information: 5509 N WOODMAN AVE 91401
- Application / Permit
- 21014-20000-00933
- Plan Check / Job No.
- B21VN02363
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 25' X 17'-1" ADDITION AND 4'-4" X 15' ADDITION TO RELOCATE BEDROOM, ADD TWO BATHROOMS, REMODEL KITCHEN, AND ENLARGE LIVING ROOM / DINING ROOM.
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- CofO Issued on 11/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 3/14/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 5/3/2021 | JEROME MAGAT PALMA |
| Issued | 5/3/2021 | APPLICANT |
| Building Plans Picked Up | 5/4/2021 | APPLICANT |
| CofO in Progress | 11/5/2021 | JENNIFER RABUCHIN |
| CofO Issued | 11/13/2021 | MICHAEL SMITH |
| Permit Finaled | 11/13/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/21/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/5/2021 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 5/11/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/18/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 5/18/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2021 | Partial Approval | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 6/8/2021 | Corrections Issued | CHARLES POWELL |
| ELECTRICAL-Rough | 6/8/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2021 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 6/8/2021 | Not Ready for Inspection | CHARLES POWELL |
| HVAC-Rough | 6/8/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/14/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/14/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/14/2021 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 6/14/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 6/17/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 6/25/2021 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/2/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/2/2021 | Approved | JENNIFER RABUCHIN |
| Final | 11/2/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 11/2/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/2/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/2/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 11/2/2021 | Approved | JENNIFER RABUCHIN |