17435 W CHASE ST 91325

Certificate Information: 17435 W CHASE ST 91325

Application / Permit
21014-20000-00929
Plan Check / Job No.
B21VN02354
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20 ' X 30' (E) ALQ AND ADD 20' X 24'-11" TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP AND ENGINEERING DETAIL.
Permit Issued
Issued on 5/13/2021
Issuing Office
Current Status
CofO Issued on 10/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/15/2021 RAPHAEL ROSAS
Corrections Issued 3/15/2021 RAPHAEL ROSAS
Issued 5/13/2021 APPLICANT
Building Plans Picked Up 5/13/2021 APPLICANT
CofO in Progress 7/2/2021 MARK JOHNSON
Permit Finaled 10/14/2021 MICHAEL SMITH
CofO Issued 10/14/2021 MICHAEL SMITH
Permit Finaled 10/14/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/19/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/22/2021 ADRIAN CASTRO
Sewer availability Cleared 3/22/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 4/28/2021 GABRIEL ROBLES
Metro Rail approval Cleared 4/30/2021 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2021 Conditional Approval MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 5/27/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/7/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 6/7/2021 Partial Approval MARK JOHNSON
Green Building Rough 6/7/2021 Approved MARK JOHNSON
Insulation 6/9/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/9/2021 Approved ALIZAH MAYAGOITIA
Drywall Nailing 6/11/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 6/11/2021 Corrections Issued MARK JOHNSON
HVAC-Rough 6/11/2021 Partial Approval MARK JOHNSON
PLUMBING-Rough 6/11/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Final 6/18/2021 Approved ARTHUR SARGSYAN
Final 6/18/2021 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 6/18/2021 Approved ARTHUR SARGSYAN
Green Building Final 6/18/2021 Approved ARTHUR SARGSYAN
HVAC-Final 6/18/2021 Approved ARTHUR SARGSYAN
PLUMBING-Final 6/18/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 6/18/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 6/18/2021 Approved ARTHUR SARGSYAN
Final 6/25/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 7/1/2021 OK to Issue CofO MARK JOHNSON