13306 W BLYTHE ST 91605
Certificate Information: 13306 W BLYTHE ST 91605
- Application / Permit
- 21014-20000-00905
- Plan Check / Job No.
- B21VN02300
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | SELLA BENYAMIN |
| Corrections Issued | 3/25/2021 | SELLA BENYAMIN |
| Quality Review Completed | 3/26/2021 | STEVEN KIM |
| Plan Check Approved | 7/1/2021 | HERNAN ARREOLA |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 1/18/2023 | GREGG CUMMINGS |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
| CofO Issued | 1/21/2023 | MICHAEL SMITH |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/6/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 6/24/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/28/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/15/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 11/15/2021 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 11/15/2021 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | GREGG CUMMINGS |
| Gas Test | 10/31/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/31/2022 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 10/31/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 11/3/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/7/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/7/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 11/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 11/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 11/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/14/2022 | Approved | WILLIAM WREN |
| Insulation | 11/14/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/14/2022 | Approved | WILLIAM WREN |
| Gas Test | 1/5/2023 | No Access for Inspection | GREGG CUMMINGS |
| Final | 1/10/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/10/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/10/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/17/2023 | Approved | GREGG CUMMINGS |
| Final | 1/17/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 1/17/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 1/17/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Approved | GREGG CUMMINGS |