5928 N TOBIAS AVE 91411

Certificate Information: 5928 N TOBIAS AVE 91411

Application / Permit
21014-20000-00902
Plan Check / Job No.
B21VN02290
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20' 5" X 18' MASTER BEDROOM/BATHROOM ADDITION TO REAR AND 8' X 15' 4" LIVING ROOM EXTENSION TO (E) SFD. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Issued on 8/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 GURUNATH NESARAJAH
Corrections Issued 3/7/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 8/3/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 9/9/2021 GURUNATH NESARAJAH
Plan Check Approved 9/20/2021 GURUNATH NESARAJAH
Issued 9/20/2021 APPLICANT
Building Plans Picked Up 9/22/2021 APPLICANT
CofO in Progress 8/17/2022 RICHARD DOCKUS
Permit Finaled 8/17/2022 MICHAEL SMITH
CofO Issued 8/17/2022 MICHAEL SMITH
Permit Finaled 8/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/20/2021 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 8/20/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 8/20/2021 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/30/2021 Approved JENNIFER RABUCHIN
Sewer 9/30/2021 Not Ready for Inspection JENNIFER RABUCHIN
Underground Mechanical 9/30/2021 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/6/2021 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 10/6/2021 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 10/28/2021 Approved RICHARD DOCKUS
ELECTRICAL-Rough 10/28/2021 Approved RICHARD DOCKUS
Green Building Rough 10/28/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 10/28/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 11/1/2021 Partial Approval RICHARD DOCKUS
Insulation 11/4/2021 Approved RICHARD DOCKUS
Drywall Nailing 11/15/2021 Approved ALAN MORELOS
Final 2/22/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 2/22/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 2/22/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 2/22/2022 Approved RICHARD DOCKUS
PLUMBING-Final 8/2/2022 Approved RICHARD DOCKUS
Final 8/15/2022 OK to Issue CofO RICHARD DOCKUS