6046 N DENNY AVE 91606
Certificate Information: 6046 N DENNY AVE 91606
- Application / Permit
- 21014-20000-00900
- Plan Check / Job No.
- B21VN02286
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 29' 9" X 24' TO (E) DETACHED GARAGE AND CONVERT TO ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/11/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 3/14/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/10/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/11/2021 | GURUNATH NESARAJAH |
| Issued | 5/11/2021 | APPLICANT |
| Building Plans Picked Up | 5/13/2021 | APPLICANT |
| CofO in Progress | 1/3/2022 | JACK KARGODORIAN |
| CofO Issued | 3/5/2022 | MICHAEL SMITH |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 4/15/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/14/2021 | Conditional Approval | JAVIER RAMOS JR |
| Underground Mechanical | 7/26/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 7/30/2021 | Conditional Approval | ALAN MORELOS |
| Deputy Drilled-In Anchors | 8/4/2021 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 8/6/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2021 | Partial Approval | DANIEL DREW |
| HVAC-Rough | 9/16/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 9/23/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 9/23/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 9/23/2021 | Approved | DANIEL DREW |
| Insulation | 10/5/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/5/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/6/2021 | Approved | DANIEL DREW |
| Green Building Rough | 10/6/2021 | Approved | DANIEL DREW |
| Insulation | 10/6/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 10/14/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 10/21/2021 | Approved | DANIEL DREW |
| Sewer | 10/21/2021 | Approved | DANIEL DREW |
| Underground Mechanical | 10/21/2021 | Approved | DANIEL DREW |
| Gas Test | 10/27/2021 | Approved | MICHEL ABAJAN |
| Final | 12/8/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Final | 12/8/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 12/8/2021 | SGSOV Not Ready | MARK JOHNSON |
| Smoke Detectors | 12/8/2021 | Not Ready for Inspection | MARK JOHNSON |
| Final | 12/15/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/15/2021 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/15/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Pre-Inspection | 12/20/2021 | Corrections Issued | DAVID MATSON |
| Final | 12/27/2021 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 12/27/2021 | Approved | JACK KARGODORIAN |
| Final | 12/29/2021 | Conditional Approval | JACK KARGODORIAN |
| Final | 1/3/2022 | OK to Issue CofO | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2022 | SGSOV Approved | JACK KARGODORIAN |