6046 N DENNY AVE 91606

Certificate Information: 6046 N DENNY AVE 91606

Application / Permit
21014-20000-00900
Plan Check / Job No.
B21VN02286
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 29' 9" X 24' TO (E) DETACHED GARAGE AND CONVERT TO ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 GURUNATH NESARAJAH
Corrections Issued 3/14/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 4/10/2021 GURUNATH NESARAJAH
Plan Check Approved 5/11/2021 GURUNATH NESARAJAH
Issued 5/11/2021 APPLICANT
Building Plans Picked Up 5/13/2021 APPLICANT
CofO in Progress 1/3/2022 JACK KARGODORIAN
CofO Issued 3/5/2022 MICHAEL SMITH
Permit Finaled 3/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/15/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/15/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/14/2021 Conditional Approval JAVIER RAMOS JR
Underground Mechanical 7/26/2021 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 7/30/2021 Conditional Approval ALAN MORELOS
Deputy Drilled-In Anchors 8/4/2021 Approved JUSTIN HAWLEY
Footing/Foundation/Slab 8/6/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Partial Approval DANIEL DREW
HVAC-Rough 9/16/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 9/23/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 9/23/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Approved DANIEL DREW
PLUMBING-Rough 9/23/2021 Approved DANIEL DREW
Insulation 10/5/2021 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 10/5/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/6/2021 Approved DANIEL DREW
Green Building Rough 10/6/2021 Approved DANIEL DREW
Insulation 10/6/2021 Approved DANIEL DREW
Drywall Nailing 10/14/2021 Approved DANIEL DREW
ELECTRICAL-Rough 10/21/2021 Approved DANIEL DREW
Sewer 10/21/2021 Approved DANIEL DREW
Underground Mechanical 10/21/2021 Approved DANIEL DREW
Gas Test 10/27/2021 Approved MICHEL ABAJAN
Final 12/8/2021 Not Ready for Inspection MARK JOHNSON
Green Building Final 12/8/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Not Ready MARK JOHNSON
Smoke Detectors 12/8/2021 Not Ready for Inspection MARK JOHNSON
Final 12/15/2021 Corrections Issued CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 12/15/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Pre-Inspection 12/20/2021 Corrections Issued DAVID MATSON
Final 12/27/2021 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/27/2021 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 12/27/2021 Approved JACK KARGODORIAN
Final 12/29/2021 Conditional Approval JACK KARGODORIAN
Final 1/3/2022 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/3/2022 SGSOV Approved JACK KARGODORIAN