7529 N LOUISE AVE 91406
Certificate Information: 7529 N LOUISE AVE 91406
- Application / Permit
- 21014-20000-00897
- Plan Check / Job No.
- B21VN02285
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 5'-5" X 11'-0" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A. 33(c) and (d)
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- Current Status
- CofO Issued on 3/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 3/14/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 4/8/2021 | JEROME MAGAT PALMA |
| Issued | 4/8/2021 | APPLICANT |
| Building Plans Picked Up | 4/19/2021 | APPLICANT |
| CofO in Progress | 3/9/2022 | RAUL OLAGI |
| Permit Finaled | 3/23/2022 | RONALD MYRICK |
| CofO Issued | 3/23/2022 | RONALD MYRICK |
| Permit Finaled | 3/23/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/18/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2021 | Partial Approval | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 7/14/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 7/14/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 10/6/2021 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/13/2021 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 10/13/2021 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/18/2021 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 10/18/2021 | Approved | RAUL OLAGI |
| Underground Mechanical | 10/18/2021 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/10/2021 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 11/10/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/10/2021 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/10/2021 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 11/10/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2021 | Approved | RAUL OLAGI |
| Insulation | 11/24/2021 | Approved | RAUL OLAGI |
| Underground Mechanical | 11/24/2021 | Approved | RAUL OLAGI |
| Drywall Nailing | 12/3/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 12/3/2021 | Partial Approval | ALAN MORELOS |
| Special/Order Compliance | 12/28/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/11/2022 | Approved | MICHAEL TEMPLE |
| Final | 2/11/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 2/11/2022 | Approved | MICHAEL TEMPLE |
| Green Building Rough | 2/11/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 2/11/2022 | SGSOV Approved | MICHAEL TEMPLE |
| Smoke Detectors | 2/11/2022 | Approved | MICHAEL TEMPLE |
| Final | 3/9/2022 | OK to Issue CofO | RAUL OLAGI |