7012 W 83RD ST 90045
Certificate Information: 7012 W 83RD ST 90045
- Application / Permit
- 21014-20000-00894
- Plan Check / Job No.
- B21VN02281
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 11'-0" x 18'-0" ADDITION TO AND CONVERT THE 18'-0" x 20'-0" (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 8/27/2021
- Issuing Office
- Current Status
- CofO Issued on 2/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 3/12/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 8/27/2021 | SARKIS HARABEDIAN |
| Issued | 8/27/2021 | APPLICANT |
| Building Plans Picked Up | 8/30/2021 | APPLICANT |
| CofO in Progress | 1/28/2022 | BOBBY KEY |
| Permit Finaled | 2/1/2022 | DANIEL ORRANTE |
| CofO Issued | 2/1/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/1/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/20/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 6/9/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/9/2021 | RIDWAN HARDY |
| Specific Plan | Cleared | 6/23/2021 | VALERIA CEJA |
| Roof/Waste drainage to street | Cleared | 7/26/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/7/2021 | Conditional Approval | SHAVONNE ESPINOZA |
| Deputy Drilled-In Anchors | 9/8/2021 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 9/17/2021 | Conditional Approval | SHAVONNE ESPINOZA |
| Sewer | 9/17/2021 | Approved | SHAVONNE ESPINOZA |
| Deputy Drilled-In Anchors | 9/21/2021 | Conditional Approval | BRENDAN LOONEY |
| Underground Mechanical | 9/21/2021 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/30/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 10/21/2021 | No Access for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 10/27/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 10/27/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 10/27/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 10/27/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 10/27/2021 | Approved | DAVID FEILER |
| Deputy Wood Construction | 11/1/2021 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 11/4/2021 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 11/4/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 11/4/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/15/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Partial Approval | RICHARD STEINBACH |
| Green Building Rough | 11/15/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Pre-Inspection | 11/15/2021 | Approved | BOBBY KEY |
| Green Building Final | 11/19/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/19/2021 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/29/2021 | Approved | BOBBY KEY |
| Green Building Rough | 11/29/2021 | Approved | BOBBY KEY |
| Insulation | 11/29/2021 | Approved | BOBBY KEY |
| Drywall Nailing | 12/7/2021 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/7/2021 | Approved | BOBBY KEY |
| Final | 1/20/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 1/20/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 1/20/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/27/2022 | Approved | BOBBY KEY |
| Final | 1/27/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 1/27/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 1/27/2022 | Approved | BOBBY KEY |
| Final | 1/28/2022 | OK to Issue CofO | BOBBY KEY |