7012 W 83RD ST 90045

Certificate Information: 7012 W 83RD ST 90045

Application / Permit
21014-20000-00894
Plan Check / Job No.
B21VN02281
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 11'-0" x 18'-0" ADDITION TO AND CONVERT THE 18'-0" x 20'-0" (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 8/27/2021
Issuing Office
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 SARKIS HARABEDIAN
Corrections Issued 3/12/2021 SARKIS HARABEDIAN
Plan Check Approved 8/27/2021 SARKIS HARABEDIAN
Issued 8/27/2021 APPLICANT
Building Plans Picked Up 8/30/2021 APPLICANT
CofO in Progress 1/28/2022 BOBBY KEY
Permit Finaled 2/1/2022 DANIEL ORRANTE
CofO Issued 2/1/2022 DANIEL ORRANTE
Permit Finaled 2/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/19/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/20/2021 DINAH GARIN
Sewer availability Cleared 5/20/2021 DINAH GARIN
Construction near power lines Cleared 6/9/2021 RIDWAN HARDY
Construction within easement Cleared 6/9/2021 RIDWAN HARDY
Specific Plan Cleared 6/23/2021 VALERIA CEJA
Roof/Waste drainage to street Cleared 7/26/2021 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/7/2021 Conditional Approval SHAVONNE ESPINOZA
Deputy Drilled-In Anchors 9/8/2021 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 9/17/2021 Conditional Approval SHAVONNE ESPINOZA
Sewer 9/17/2021 Approved SHAVONNE ESPINOZA
Deputy Drilled-In Anchors 9/21/2021 Conditional Approval BRENDAN LOONEY
Underground Mechanical 9/21/2021 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 9/30/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Drilled-In Anchors 10/21/2021 No Access for Inspection DAVID FEILER
BUILDING-Rough-Frame 10/27/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 10/27/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval DAVID FEILER
Green Building Rough 10/27/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 10/27/2021 Approved DAVID FEILER
PLUMBING-Rough 10/27/2021 Approved DAVID FEILER
Deputy Wood Construction 11/1/2021 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 11/4/2021 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Approved BRENDAN LOONEY
Green Building Rough 11/4/2021 Not Ready for Inspection BRENDAN LOONEY
Shower Pan 11/4/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 11/15/2021 Not Ready for Inspection RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval RICHARD STEINBACH
Green Building Rough 11/15/2021 Not Ready for Inspection RICHARD STEINBACH
Pre-Inspection 11/15/2021 Approved BOBBY KEY
Green Building Final 11/19/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/19/2021 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 11/29/2021 Approved BOBBY KEY
Green Building Rough 11/29/2021 Approved BOBBY KEY
Insulation 11/29/2021 Approved BOBBY KEY
Drywall Nailing 12/7/2021 Approved BOBBY KEY
Interior/Exterior Lathing 12/7/2021 Approved BOBBY KEY
Final 1/20/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/20/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 1/20/2022 Approved BOBBY KEY
ELECTRICAL-Final 1/27/2022 Approved BOBBY KEY
Final 1/27/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 1/27/2022 Approved BOBBY KEY
PLUMBING-Final 1/27/2022 Approved BOBBY KEY
Final 1/28/2022 OK to Issue CofO BOBBY KEY