6838 N NESTLE AVE 91335
Certificate Information: 6838 N NESTLE AVE 91335
- Application / Permit
- 21014-20000-00873
- Plan Check / Job No.
- B21VN02240
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 17'3" X 23'4"ADDITION TO AND CONVERT THE (E) 20'4" X 20'4" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT AS PER LAMC12.22.A.33 (C) AND (E), ALL WORK PER WFPP
- Permit Issued
- Issued on 9/29/2021
- Issuing Office
- Current Status
- CofO Issued on 8/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | KAVIAN REFAHI |
| Corrections Issued | 3/20/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/24/2021 | RARES BODEA |
| Plan Check Approved | 9/28/2021 | RARES BODEA |
| Issued | 9/29/2021 | APPLICANT |
| Building Plans Picked Up | 10/4/2021 | APPLICANT |
| CofO in Progress | 8/1/2023 | JEFFREY BULL |
| Permit Finaled | 8/1/2023 | JOHN JANSON |
| CofO Issued | 8/1/2023 | JOHN JANSON |
| Permit Finaled | 8/1/2023 | JOHN JANSON |
Permit Application Clearance Information
| Construction within easement | Cleared | 6/8/2021 | RIDWAN HARDY |
| Address approval | Cleared | 6/11/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/11/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/14/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/3/2021 | RUEL COLE |
| ZI | Cleared | 9/7/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2021 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 11/29/2021 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 4/14/2022 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/6/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/6/2022 | Approved | VINCENT HANLEY |
| Sewer | 6/15/2022 | Partial Approval | JEFFREY BULL |
| Deputy Drilled-In Anchors | 6/17/2022 | Conditional Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2022 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/12/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/12/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 10/12/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 10/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 10/27/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 10/27/2022 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 10/27/2022 | Partial Approval | JEFFREY BULL |
| Insulation | 11/2/2022 | Approved | JEFFREY BULL |
| Drywall Nailing | 12/5/2022 | Approved | JEFFREY BULL |
| Shower Pan | 12/5/2022 | Approved | JEFFREY BULL |
| Gas Test | 3/7/2023 | Not Ready for Inspection | JEFFREY BULL |
| Sewer | 3/7/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 7/10/2023 | Approved | PETER FOLLING |
| Final | 7/10/2023 | Corrections Issued | PETER FOLLING |
| Gas Test | 7/10/2023 | Approved | PETER FOLLING |
| Green Building Final | 7/10/2023 | Approved | PETER FOLLING |
| Green Building Rough | 7/10/2023 | Approved | PETER FOLLING |
| Smoke Detectors | 7/10/2023 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 7/19/2023 | Approved | JEFFREY BULL |
| Final | 7/19/2023 | OK to Issue CofO | JEFFREY BULL |
| HVAC-Final | 7/19/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 7/19/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | JEFFREY BULL |