23518 W SPIRES ST 91304

Certificate Information: 23518 W SPIRES ST 91304

Application / Permit
21014-20000-00857
Plan Check / Job No.
B21VN02208
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remove (e) 15' x 23' attached sunroom, and add 15' x 23'-6" addition and add 12' x 23'-6" patio cover to (e) SFD
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
CofO Issued on 11/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 MOHAMMAD ESMAILI
Corrections Issued 3/6/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 3/10/2021 APPLICANT
Plan Check Approved 1/27/2022 MOHAMMAD ESMAILI
Issued 2/8/2022 APPLICANT
CofO in Progress 10/13/2022 CHRIS CHRISTENSEN
Permit Finaled 11/3/2022 JOHN JANSON
CofO Issued 11/3/2022 JOHN JANSON
Permit Finaled 11/3/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2021 GUILLERMO PETRA
Grading Pre-Inspection Cleared 6/1/2021 KIRK LINKLATER
Low Impact Development Cleared 12/28/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/29/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/16/2022 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 4/1/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/5/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/11/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Partial Approval CHRIS CHRISTENSEN
Insulation 4/19/2022 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 4/20/2022 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/27/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 4/27/2022 Approved CHRIS CHRISTENSEN
Wood Frame 4/27/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/2/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 5/2/2022 Approved CHRIS CHRISTENSEN
Insulation 5/2/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/2/2022 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 5/5/2022 Approved JESUS PINEDA
Final 7/27/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/27/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 7/27/2022 Approved CHRIS CHRISTENSEN
Final 9/20/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 9/20/2022 Approved CHRIS CHRISTENSEN
Final 10/12/2022 OK to Issue CofO CHRIS CHRISTENSEN