5350 N CREBS AVE 91356
Certificate Information: 5350 N CREBS AVE 91356
- Application / Permit
- 21014-20000-00838
- Plan Check / Job No.
- B21VN02173
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 10'3" X 19'10" ADDITION TO THE REAR OF THE (E) SFD TO CREATE NEW DEN, BATHROOM AND LAUNDRY ROOM , ALL WORK PER WFPP
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- CofO Issued on 6/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | RARES BODEA |
| Corrections Issued | 3/7/2021 | RARES BODEA |
| Plan Check Approved | 6/11/2021 | RARES BODEA |
| Issued | 6/22/2021 | APPLICANT |
| Building Plans Picked Up | 7/21/2021 | APPLICANT |
| CofO in Progress | 6/21/2023 | SEAN HAUPT |
| CofO Issued | 6/21/2023 | JOHN JANSON |
| Permit Finaled | 6/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/6/2021 | RARES BODEA |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 4/12/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Hi - Teck; Lic. No.: 884146-B | 14001 VENTURA BLVD SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/6/2021 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 8/9/2021 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 8/11/2021 | Partial Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 8/11/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 9/16/2021 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2021 | Approved | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 9/16/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 10/1/2021 | Corrections Issued | DAVID SANDOVAL |
| Interior/Exterior Lathing | 10/1/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 10/20/2021 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 10/20/2021 | Approved | JAVIER RAMOS JR |
| Insulation | 10/20/2021 | Approved | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 10/20/2021 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 11/16/2021 | Approved | DAVID SANDOVAL |
| Final | 3/23/2023 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 3/23/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 3/23/2023 | Approved | DAVID SANDOVAL |
| Final | 6/20/2023 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 6/20/2023 | Approved | SEAN HAUPT |