1546 N ALEXANDRIA AVE 90027

Certificate Information: 1546 N ALEXANDRIA AVE 90027

Application / Permit
21014-20000-00826
Plan Check / Job No.
B21VN02132
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(c) OVER (E) DETACHED CARPORT
Permit Issued
Issued on 11/1/2021
Issuing Office
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 NILOOFAR MEHRAIN
Corrections Issued 3/18/2021 NILOOFAR MEHRAIN
Quality Review Completed 3/22/2021 CHON CHIO KUO
Applicant returned to address corrections 9/16/2021 NILOOFAR MEHRAIN
Plan Check Approved 9/29/2021 NILOOFAR MEHRAIN
Issued 11/1/2021 APPLICANT
CofO in Progress 9/5/2024 RAFAEL CORTES
CofO Issued 9/6/2024 ERNESTO CORRAL
Permit Finaled 9/6/2024 ERNESTO CORRAL

Permit Application Clearance Information

Specific Plan Cleared 4/1/2021 DANALYNN DOMINGUEZ
ZI Cleared 4/1/2021 DANALYNN DOMINGUEZ
Hydrant and Access approval Cleared 5/19/2021 MATTHEW CRAIG
Low Impact Development Cleared 9/5/2021 JORGE MEJIA LEMUS
Address approval Cleared 9/9/2021 NAZILA NOORIFAR
Roof/Waste drainage to street Cleared 9/9/2021 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 9/10/2021 NAZILA NOORIFAR
Sewer availability Cleared 9/10/2021 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/23/2022 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 1/24/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/6/2023 Corrections Issued JOAQUIN GREENOUGH
Deputy Reinf. Concrete 2/7/2023 Conditional Approval JOAQUIN GREENOUGH
Deputy Steel/Welding 2/10/2023 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/10/2023 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 5/4/2023 Approved RONALD JIMENEZ
Special/Order Compliance 5/8/2023 Approved RONALD JIMENEZ
Masonry Wall/Backfill 5/18/2023 Partial Approval RONALD JIMENEZ
Reinforced Masonry Frame 5/18/2023 Partial Approval RONALD JIMENEZ
Deputy Steel/Welding 5/31/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 6/1/2023 Not Ready for Inspection TIMOTHY POWELL
Reinforced Concrete Frame 6/1/2023 Not Ready for Inspection TIMOTHY POWELL
Masonry Wall/Backfill 6/2/2023 Not Ready for Inspection TIMOTHY POWELL
Masonry Wall/Backfill 6/5/2023 Corrections Issued TIMOTHY POWELL
Deputy Steel/Welding 6/13/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 6/21/2023 Partial Approval TIMOTHY POWELL
Reinforced Masonry Frame 6/21/2023 Partial Approval TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Approved RONALD JIMENEZ
Wood Frame 7/24/2023 Not Ready for Inspection RONALD JIMENEZ
Deputy Wood Construction 10/10/2023 Conditional Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Approved RONALD JIMENEZ
Wood Frame 10/10/2023 Partial Approval RONALD JIMENEZ
Insulation 10/18/2023 Approved JACOB MYERS
Interior/Exterior Lathing 10/20/2023 Partial Approval RICARDO ROBLES
Drywall Nailing 10/27/2023 Approved RICARDO ROBLES
BUILDING-Rough-Frame 7/18/2024 Approved RAFAEL CORTES
Final 7/18/2024 Not Ready for Inspection RAFAEL CORTES
Green Building Final 7/18/2024 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 7/18/2024 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 7/18/2024 Approved RAFAEL CORTES
Structural Steel Frame 7/18/2024 Approved RAFAEL CORTES
Final 7/23/2024 Not Ready for Inspection RAFAEL CORTES
Green Building Final 7/23/2024 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 7/23/2024 SGSOV Not Ready RAFAEL CORTES
Final 7/29/2024 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved RAFAEL CORTES
Final 8/6/2024 Not Ready for Inspection RAFAEL CORTES
Final 8/22/2024 Conditional Approval RAFAEL CORTES
Final 9/4/2024 OK to Issue CofO RAFAEL CORTES