1546 N ALEXANDRIA AVE 90027
Certificate Information: 1546 N ALEXANDRIA AVE 90027
- Application / Permit
- 21014-20000-00826
- Plan Check / Job No.
- B21VN02132
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(c) OVER (E) DETACHED CARPORT
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 9/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/18/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/22/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/16/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/29/2021 | NILOOFAR MEHRAIN |
| Issued | 11/1/2021 | APPLICANT |
| CofO in Progress | 9/5/2024 | RAFAEL CORTES |
| CofO Issued | 9/6/2024 | ERNESTO CORRAL |
| Permit Finaled | 9/6/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/1/2021 | DANALYNN DOMINGUEZ |
| ZI | Cleared | 4/1/2021 | DANALYNN DOMINGUEZ |
| Hydrant and Access approval | Cleared | 5/19/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/5/2021 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 9/9/2021 | NAZILA NOORIFAR |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2021 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 9/10/2021 | NAZILA NOORIFAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/23/2022 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 1/24/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/6/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 2/7/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Steel/Welding | 2/10/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/10/2023 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/4/2023 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 5/8/2023 | Approved | RONALD JIMENEZ |
| Masonry Wall/Backfill | 5/18/2023 | Partial Approval | RONALD JIMENEZ |
| Reinforced Masonry Frame | 5/18/2023 | Partial Approval | RONALD JIMENEZ |
| Deputy Steel/Welding | 5/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Masonry Wall/Backfill | 6/1/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Reinforced Concrete Frame | 6/1/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Masonry Wall/Backfill | 6/2/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Masonry Wall/Backfill | 6/5/2023 | Corrections Issued | TIMOTHY POWELL |
| Deputy Steel/Welding | 6/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Masonry Wall/Backfill | 6/21/2023 | Partial Approval | TIMOTHY POWELL |
| Reinforced Masonry Frame | 6/21/2023 | Partial Approval | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Approved | RONALD JIMENEZ |
| Wood Frame | 7/24/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Deputy Wood Construction | 10/10/2023 | Conditional Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Approved | RONALD JIMENEZ |
| Wood Frame | 10/10/2023 | Partial Approval | RONALD JIMENEZ |
| Insulation | 10/18/2023 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 10/20/2023 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 10/27/2023 | Approved | RICARDO ROBLES |
| BUILDING-Rough-Frame | 7/18/2024 | Approved | RAFAEL CORTES |
| Final | 7/18/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 7/18/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 7/18/2024 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 7/18/2024 | Approved | RAFAEL CORTES |
| Structural Steel Frame | 7/18/2024 | Approved | RAFAEL CORTES |
| Final | 7/23/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 7/23/2024 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/23/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Final | 7/29/2024 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | RAFAEL CORTES |
| Final | 8/6/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 8/22/2024 | Conditional Approval | RAFAEL CORTES |
| Final | 9/4/2024 | OK to Issue CofO | RAFAEL CORTES |