- PROPOSE TWO STORY ADDITION TO (E) ONE STORY SFD WITH ATTACH PORCH AND REMODEL_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 10/4/2021
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | DAWN MC NULTY |
| Corrections Issued | 3/22/2021 | DAWN MC NULTY |
| Quality Review Completed | 3/22/2021 | CHON CHIO KUO |
| Plan Check Approved | 8/30/2021 | DAWN MC NULTY |
| Issued | 10/4/2021 | APPLICANT |
| CofO in Progress | 5/19/2023 | SEAN HAUPT |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
| CofO Issued | 4/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/6/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/19/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 8/12/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/14/2021 | ABDULLAH SADOZAI |
| GPI Written Notices | Cleared | 8/30/2021 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 8/30/2021 | DAWN MC NULTY |
Contact Information
| Contractor | So Cal Builders And Design Inc; Lic. No.: 990258-B | 15335 MORRISON STREET #375 SHERMAN OAKS, CA 91403 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/1/2021 | Partial Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/8/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/19/2021 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 11/19/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 2/22/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 2/22/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 2/22/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 4/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 4/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/18/2022 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/18/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 4/18/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 4/18/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 4/18/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 5/10/2022 | Corrections Issued | DAVID SANDOVAL |
| Insulation | 6/2/2022 | Not Ready for Inspection | MORRIS JACKSON |
| Insulation | 6/9/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/9/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/29/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 6/29/2022 | Approved | DAVID SANDOVAL |
| Special/Order Compliance | 6/29/2022 | Partial Inspection | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 6/29/2022 | Approved | DAVID SANDOVAL |
| Shower Pan | 6/30/2022 | Not Ready for Inspection | MORRIS JACKSON |
| Pre-Inspection | 7/1/2022 | Not Ready for Inspection | MORRIS JACKSON |
| Shower Pan | 7/1/2022 | Not Ready for Inspection | MORRIS JACKSON |
| Drywall Nailing | 7/5/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/5/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 7/5/2022 | Approved | MORRIS JACKSON |
| Final | 10/31/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 10/31/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 10/31/2022 | Approved | DAVID SANDOVAL |
| Final | 1/27/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 1/27/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 4/18/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 4/18/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Pre-Inspection | 4/18/2023 | Partial Inspection | JUSTIN HAWLEY |
| Final | 4/26/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 4/26/2023 | Approved | SEAN HAUPT |
| Final | 5/18/2023 | OK to Issue CofO | SEAN HAUPT |