12436 W SYLVAN ST 91606
Certificate Information: 12436 W SYLVAN ST 91606
- Application / Permit
- 21014-20000-00799
- Plan Check / Job No.
- B21VN02053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXPAND (E) KITCHEN, ADD (N) BATHROOM & LAUNDRY (24' X 10'-6") PER ENG'R DESIGN
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/7/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/27/2021 | NILOOFAR MEHRAIN |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 3/29/2023 | ARAM AVEDISIAN |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/13/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/30/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/30/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/5/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 8/16/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 8/16/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/16/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/23/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 10/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 10/18/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 10/26/2021 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 10/26/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/3/2021 | Approved | ASHLEY THOMPSON |
| Final | 2/7/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 2/7/2022 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Final | 2/7/2022 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 2/7/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 3/14/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/14/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 3/24/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/24/2022 | Approved | CHRISTOPHE COCHRAN |