979 S WESTCHESTER PL 90019
Certificate Information: 979 S WESTCHESTER PL 90019
- Application / Permit
- 21014-20000-00790
- Plan Check / Job No.
- B21VN02019
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-4" x 17'-5" (2) STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 11/25/2021
- Issuing Office
- Current Status
- CofO Issued on 8/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | SELLA BENYAMIN |
| Corrections Issued | 3/12/2021 | SELLA BENYAMIN |
| Quality Review Completed | 3/18/2021 | STEVEN KIM |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| Applicant returned to address corrections | 7/27/2021 | SELLA BENYAMIN |
| Plan Check Approved | 10/5/2021 | SELLA BENYAMIN |
| Issued | 11/25/2021 | APPLICANT |
| CofO in Progress | 5/26/2025 | JEFFREY MEAD |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| CofO Issued | 8/24/2025 | DEROLD HAUFF |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/30/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/30/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2021 | JEANIE LAM |
| HPOZ | Cleared | 6/23/2021 | AMANDA KAINER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/2/2022 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | JEFFREY MEAD |
| Insulation | 8/22/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/1/2022 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/14/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/14/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 3/14/2023 | Approved | JEFFREY MEAD |
| METHANE-Rough | 3/14/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/14/2023 | Approved | JEFFREY MEAD |
| Insulation | 3/16/2023 | Approved | JEFFREY MEAD |
| Insulation | 3/17/2023 | No Access for Inspection | JEFFREY MEAD |
| Drywall Nailing | 3/31/2023 | Approved | JEFFREY MEAD |
| Shower Pan | 3/31/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 4/14/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 8/2/2024 | Approved | JEFFREY MEAD |
| Final | 8/2/2024 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/2/2024 | Approved | JEFFREY MEAD |
| Green Building Final | 8/2/2024 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 8/2/2024 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 8/2/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 8/2/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 8/2/2024 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 5/20/2025 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Final | 5/23/2025 | Approved | JEFFREY MEAD |
| Final | 5/23/2025 | OK to Issue CofO | JEFFREY MEAD |
| HVAC-Final | 5/23/2025 | Approved | JEFFREY MEAD |