10874 N ARLETA AVE 91345
Certificate Information: 10874 N ARLETA AVE 91345
- Application / Permit
- 21014-20000-00784
- Plan Check / Job No.
- B21VN01993
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE (E) BREEZEWAY BETWEEN SFD & ATT. GARAGE, ADD (9'-2"x 19'-3") IRR SHAPE KITCHEN @ FRONT & ADD (15'-8"x 19'3") MASTER BED / BATH @ REAR OF 1ST FLOOR & ADD (28'-5"x 19'-3") 2ND STORY WITH OPEN BALCONY AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | TROY DEGUZMAN |
| Corrections Issued | 3/16/2021 | TROY DEGUZMAN |
| Quality Review Completed | 3/22/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/27/2021 | TROY DEGUZMAN |
| Plan Check Approved | 7/29/2021 | TROY DEGUZMAN |
| Plan Check Approved | 8/3/2021 | TROY DEGUZMAN |
| Issued | 5/11/2022 | APPLICANT |
| CofO in Progress | 12/19/2022 | JENNIFER RABUCHIN |
| CofO Issued | 1/25/2023 | MICHAEL SMITH |
| Permit Finaled | 1/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/24/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 5/21/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 6/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/30/2021 | GABRIEL ROBLES |
| Green Code | Cleared | 7/27/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/23/2022 | Partial Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/15/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/21/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 6/21/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 6/21/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/18/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/25/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/29/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/29/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/10/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/10/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 11/10/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/10/2022 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 11/10/2022 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Final | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/10/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/22/2022 | Approved | JENNIFER RABUCHIN |
| Final | 11/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 11/22/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 11/22/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 12/16/2022 | OK to Issue CofO | JENNIFER RABUCHIN |