10874 N ARLETA AVE 91345

Certificate Information: 10874 N ARLETA AVE 91345

Application / Permit
21014-20000-00784
Plan Check / Job No.
B21VN01993
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE (E) BREEZEWAY BETWEEN SFD & ATT. GARAGE, ADD (9'-2"x 19'-3") IRR SHAPE KITCHEN @ FRONT & ADD (15'-8"x 19'3") MASTER BED / BATH @ REAR OF 1ST FLOOR & ADD (28'-5"x 19'-3") 2ND STORY WITH OPEN BALCONY AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 1/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 TROY DEGUZMAN
Corrections Issued 3/16/2021 TROY DEGUZMAN
Quality Review Completed 3/22/2021 OMID HEDAYAT
Applicant returned to address corrections 7/27/2021 TROY DEGUZMAN
Plan Check Approved 7/29/2021 TROY DEGUZMAN
Plan Check Approved 8/3/2021 TROY DEGUZMAN
Issued 5/11/2022 APPLICANT
CofO in Progress 12/19/2022 JENNIFER RABUCHIN
CofO Issued 1/25/2023 MICHAEL SMITH
Permit Finaled 1/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/24/2021 ADRIAN CASTRO
Sewer availability Cleared 3/24/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 5/21/2021 KURT CORRAL
Low Impact Development Cleared 6/30/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/30/2021 GABRIEL ROBLES
Green Code Cleared 7/27/2021 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Moradian,, Helbert; Lic. No.: C76618 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/23/2022 Partial Inspection JENNIFER RABUCHIN
PLUMBING-Rough 6/15/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 6/21/2022 Approved JENNIFER RABUCHIN
METHANE-Barrier 6/21/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 6/21/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/18/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/18/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 7/18/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 7/18/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/18/2022 Corrections Issued JENNIFER RABUCHIN
Sewer 7/18/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 7/18/2022 Approved JENNIFER RABUCHIN
Insulation 7/25/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/25/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 7/29/2022 Approved JENNIFER RABUCHIN
Shower Pan 7/29/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/10/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/10/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/10/2022 Corrections Issued JENNIFER RABUCHIN
Final 11/10/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/10/2022 Approved JENNIFER RABUCHIN
Green Building Rough 11/10/2022 Approved JENNIFER RABUCHIN
HVAC-Final 11/10/2022 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 11/10/2022 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 11/10/2022 Approved JENNIFER RABUCHIN
METHANE-Final 11/10/2022 Approved JENNIFER RABUCHIN
METHANE-Rough 11/10/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/10/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 11/10/2022 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 11/10/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/22/2022 Approved JENNIFER RABUCHIN
Final 11/22/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Final 11/22/2022 Approved JENNIFER RABUCHIN
MERV13>=Final 11/22/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved JENNIFER RABUCHIN
Final 12/16/2022 OK to Issue CofO JENNIFER RABUCHIN