17226 W KITTRIDGE ST 91406

Certificate Information: 17226 W KITTRIDGE ST 91406

Application / Permit
21014-20000-00774
Plan Check / Job No.
B21VN01981
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (5'-1"x 12'-0") FULL BATHROOM TO THE (E) ONE-STORY SINGLE FAMILY DWELLIN. WORK PER ENGINEER.
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 9/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 TROY DEGUZMAN
Corrections Issued 3/7/2021 TROY DEGUZMAN
Applicant returned to address corrections 3/15/2021 HAYATO TSUCHIYA
Building Plans Picked Up 3/17/2021 APPLICANT
Plan Check Approved 3/23/2021 TROY DEGUZMAN
Issued 3/23/2021 APPLICANT
CofO in Progress 9/21/2021 STEVEN BACK
Permit Finaled 9/22/2021 MICHAEL SMITH
CofO Issued 9/22/2021 MICHAEL SMITH
Permit Finaled 9/22/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/11/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/11/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/11/2021 JOHN TRIANTAFYLLOS

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Nexxus Remodeling Inc; Lic. No.: 822320-B P O BOX 260470      ENCINO, CA 91426

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/9/2021 Approved STEVEN BACK
Footing/Foundation/Slab 4/9/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 4/16/2021 Partial Approval STEVEN BACK
Green Building Rough 4/16/2021 Not Ready for Inspection STEVEN BACK
Insulation 4/16/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 4/16/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/19/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 4/30/2021 Approved STEVEN BACK
ELECTRICAL-Rough 4/30/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/30/2021 Approved STEVEN BACK
PLUMBING-Rough 4/30/2021 Approved STEVEN BACK
Insulation 5/5/2021 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 5/5/2021 Approved LILIANA PORTILLO
Pre-Inspection 5/5/2021 Partial Inspection STEPHANIE SWANSON
Shower Pan 5/5/2021 Approved LILIANA PORTILLO
Special/Order Compliance 5/5/2021 Partial Inspection STEPHANIE SWANSON
Drywall Nailing 5/10/2021 Approved JESUS PINEDA
Pre-Inspection 5/10/2021 Partial Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 5/13/2021 Approved STEVEN BACK
Green Building Rough 5/13/2021 Approved STEVEN BACK
Final 6/21/2021 Corrections Issued STEVEN BACK
Green Building Final 6/21/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/21/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 6/21/2021 Corrections Issued STEVEN BACK
Final 9/21/2021 OK to Issue CofO STEVEN BACK
Smoke Detectors 9/21/2021 Approved STEVEN BACK