5506 N COLUMBUS AVE 91411
Certificate Information: 5506 N COLUMBUS AVE 91411
- Application / Permit
- 21014-20000-00769
- Plan Check / Job No.
- B21VN01969
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL; REMOVE SINGLE FAMILY DWELLING EXCEPT FOR 5'-8" WALL LENGTH ON SOUTH SIDE OF LOT; ADD 38' X 60'-7" SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 8/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | SELLA BENYAMIN |
| Corrections Issued | 4/5/2021 | SELLA BENYAMIN |
| Quality Review Completed | 4/7/2021 | STEVEN KIM |
| Plan Check Approved | 10/26/2021 | SELLA BENYAMIN |
| Issued | 11/4/2021 | APPLICANT |
| CofO in Progress | 6/29/2022 | JACK KARGODORIAN |
| Permit Finaled | 8/5/2022 | DEROLD HAUFF |
| CofO Issued | 8/5/2022 | DEROLD HAUFF |
| Permit Finaled | 8/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 6/30/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/1/2021 | GABRIEL ROBLES |
| ZI | Cleared | 7/1/2021 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 9/6/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 10/5/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | GABRIEL ROBLES |
| Trees in Parkway | Cleared | 10/9/2021 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/18/2021 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 11/18/2021 | Partial Approval | JACK KARGODORIAN |
| METHANE-Subgrade | 11/23/2021 | Corrections Issued | MICHAEL TEMPLE |
| METHANE-Subgrade | 12/2/2021 | Approved | JACK KARGODORIAN |
| Deputy Methane Barrier | 12/8/2021 | Partial Approval | JACK KARGODORIAN |
| Deputy Methane Barrier | 12/10/2021 | Approved | JACK KARGODORIAN |
| METHANE-Barrier | 12/10/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/20/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| METHANE-Barrier | 12/20/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/22/2021 | Approved | JACK KARGODORIAN |
| METHANE-Barrier | 12/22/2021 | Approved | JACK KARGODORIAN |
| METHANE-Subgrade | 12/22/2021 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2022 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 2/1/2022 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 2/10/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 2/10/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/14/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/16/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 2/16/2022 | Approved | JACK KARGODORIAN |
| METHANE-Rough | 2/16/2022 | Approved | JACK KARGODORIAN |
| Insulation | 2/28/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/28/2022 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 3/8/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/8/2022 | Approved | JACK KARGODORIAN |
| Shower Pan | 3/8/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 3/11/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 6/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 6/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 6/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 6/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 6/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 6/23/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 6/23/2022 | Approved | JACK KARGODORIAN |
| HVAC-Final | 6/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 6/23/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 6/23/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 6/29/2022 | Approved | JACK KARGODORIAN |
| Final | 6/29/2022 | OK to Issue CofO | JACK KARGODORIAN |
| HVAC-Final | 6/29/2022 | Approved | JACK KARGODORIAN |
| Service/Power Release | 6/29/2022 | Approved | JACK KARGODORIAN |