3801 S BUCKINGHAM ROAD 90008
Certificate Information: 3801 S BUCKINGHAM ROAD 90008
- Application / Permit
- 21014-20000-00746
- Plan Check / Job No.
- B21VN01925
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 11'-7' X 15' ADDITION AND REMODEL TO (E) 1 STORY SINGLE FAMILY DEWLLING. ALL WORK PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- CofO Issued on 6/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/12/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/21/2022 | AUNG SOE |
| Plan Check Approved | 1/24/2022 | AUNG SOE |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| Issued | 3/10/2022 | APPLICANT |
| CofO in Progress | 6/15/2023 | ANTHONY EGSON |
| Permit Finaled | 6/18/2023 | DEROLD HAUFF |
| CofO Issued | 6/18/2023 | DEROLD HAUFF |
| Permit Finaled | 6/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/25/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/29/2021 | CECILIO NAVARRO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | So Cal Builders And Design Inc; Lic. No.: 990258-B | 15335 MORRISON STREET #375 SHERMAN OAKS, CA 91403 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/30/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/27/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/2/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/2/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/25/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/1/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 8/1/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/1/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/4/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 8/4/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 8/4/2022 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 8/9/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/17/2022 | Approved | ANTHONY EGSON |
| Insulation | 8/25/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/31/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 9/6/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/8/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 11/16/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/22/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 11/22/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/7/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 3/7/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/7/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/7/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 3/7/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 5/1/2023 | Approved | ANTHONY EGSON |
| Final | 5/1/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/1/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 5/1/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 5/1/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 5/1/2023 | Approved | ANTHONY EGSON |
| Final | 5/31/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 6/15/2023 | OK to Issue CofO | ANTHONY EGSON |