11211 W BLIX ST 91602

Certificate Information: 11211 W BLIX ST 91602

Application / Permit
21014-20000-00745
Plan Check / Job No.
B21VN01924
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRREGULAR SHAPED 37-4" X 15'-10" 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/1/2022
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 3/23/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/14/2021 OMID HEDAYAT
Plan Check Approved 11/3/2021 SEWADA ZADOORAN MILAGARDI
Issued 4/1/2022 APPLICANT
CofO in Progress 2/21/2023 JACK KARGODORIAN
CofO Issued 3/4/2023 MICHAEL SMITH
Permit Finaled 3/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/3/2021 LEE GUILBEAUX
Sewer availability Cleared 8/24/2021 LEE GUILBEAUX
Low Impact Development Cleared 10/19/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 10/25/2021 ABDULLAH SADOZAI

Contact Information

Contractor So Cal Elite Homes Inc; Lic. No.: 530553-B 28445 NICHOLAS CR      SAUGUS, CA 91350
Engineer Sayah,, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/29/2022 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 4/29/2022 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/9/2022 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 6/16/2022 Approved THOMAS FINNILA
Deputy Wood Construction 8/22/2022 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 8/24/2022 Corrections Issued CALEB MEISTER
Green Building Rough 8/24/2022 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 8/24/2022 Corrections Issued CALEB MEISTER
Deputy Wood Construction 8/29/2022 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Partial Approval ALAN MORELOS
Rough-Elec/Plmb/HVAC 8/29/2022 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 9/2/2022 Not Ready for Inspection CALEB MEISTER
Insulation 9/7/2022 Approved DAVID MATSON
Interior/Exterior Lathing 9/7/2022 Partial Approval DAVID MATSON
Drywall Nailing 9/13/2022 Approved ALAN MORELOS
Green Building Rough 9/13/2022 Approved ALAN MORELOS
Shower Pan 9/20/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 12/27/2022 Approved JACK KARGODORIAN
Final 12/27/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 12/27/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 12/27/2022 Approved JACK KARGODORIAN
Final 2/17/2023 OK to Issue CofO JACK KARGODORIAN