4740 N ARCOLA AVE 91602
Certificate Information: 4740 N ARCOLA AVE 91602
- Application / Permit
- 21014-20000-00744
- Plan Check / Job No.
- B21VN01915
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRR. SHAPED ADDITION (716.44 SF) & REMODEL TO (E) SINGLE FAMILY DWELLING W/ ATT. GARAGE AND ADD NEW TRELLIS IN THE REAR; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 10/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/16/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 3/30/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/9/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 7/13/2021 | SEAN SHAHMIRI |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 9/23/2022 | JOHN HAYES |
| CofO Issued | 10/29/2022 | MICHAEL SMITH |
| Permit Finaled | 10/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/7/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 6/10/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/25/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Mc Caslin Vernon Lamar; Lic. No.: 572131-B | 1025 OLIVE ST #35 SANTA BARBARA, CA 93101 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/9/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 8/9/2021 | Approved | DANIEL DREW |
| Insulation | 9/10/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/15/2021 | Partial Approval | DANIEL DREW |
| Insulation | 9/15/2021 | Partial Approval | DANIEL DREW |
| PLUMBING-Rough | 9/15/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 1/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 1/28/2022 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/10/2022 | Corrections Issued | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 2/10/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/25/2022 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 2/25/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 2/25/2022 | Approved | CALEB MEISTER |
| Insulation | 2/25/2022 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 2/25/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 3/4/2022 | Approved | CALEB MEISTER |
| Insulation | 3/4/2022 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 3/4/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 3/14/2022 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/12/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 8/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/26/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 8/26/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 8/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 9/23/2022 | Approved | JOHN HAYES |
| Final | 9/23/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 9/23/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 9/23/2022 | Approved | JOHN HAYES |