8754 N SNOWDEN AVE 91331
Certificate Information: 8754 N SNOWDEN AVE 91331
- Application / Permit
- 21014-20000-00743
- Plan Check / Job No.
- B21VN01914
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 139.75 SQ. FT. ADDITION TO AND CONVERT THE (E) 360 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (D). CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 8/10/2021
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2021 | KAVIAN REFAHI |
| Corrections Issued | 3/13/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 6/9/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 7/21/2021 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/27/2021 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| Issued | 8/10/2021 | APPLICANT |
| CofO in Progress | 9/15/2022 | ARAM AVEDISIAN |
| Permit Finaled | 10/12/2022 | MICHAEL SMITH |
| CofO Issued | 10/12/2022 | MICHAEL SMITH |
| Permit Finaled | 10/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 4/20/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/21/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 5/24/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 7/6/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/15/2021 | Conditional Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/18/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 11/18/2021 | Partial Inspection | WILLIAM KUEHN |
| ELECTRICAL-Rough | 1/12/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 1/12/2022 | Approved | GREGG CUMMINGS |
| Sewer | 1/12/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 1/12/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/2/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/2/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/2/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 2/2/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/17/2022 | Approved | GREGG CUMMINGS |
| Insulation | 2/25/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 2/25/2022 | Partial Inspection | GREGG CUMMINGS |
| Shower Pan | 2/25/2022 | Approved | GREGG CUMMINGS |
| Insulation | 3/14/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/14/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 3/21/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/21/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/21/2022 | Approved | GREGG CUMMINGS |
| Final | 9/15/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 9/15/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 9/15/2022 | Approved | ARAM AVEDISIAN |