14314 W OSBORNE ST 91402
Certificate Information: 14314 W OSBORNE ST 91402
- Application / Permit
- 21014-20000-00741
- Plan Check / Job No.
- B21VN01909
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 22'-8"x10'-0", 227 SQ. FT. ADDITION TO THE REAR OF THE (E) SFD, AND INTERIOR REMODEL TO THE (E) KITCHEN. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | COLIN LOREDO |
| Corrections Issued | 3/7/2021 | COLIN LOREDO |
| Building Plans Picked Up | 3/16/2021 | APPLICANT |
| Plan Check Approved | 7/21/2021 | COLIN LOREDO |
| Issued | 7/21/2021 | APPLICANT |
| CofO in Progress | 4/20/2022 | GREGG CUMMINGS |
| Permit Finaled | 6/14/2022 | DANIEL ORRANTE |
| CofO Issued | 6/14/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/14/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/16/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2021 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/3/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/3/2021 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2021 | Partial Approval | GREGG CUMMINGS |
| Insulation | 9/14/2021 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 9/14/2021 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2021 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/7/2021 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 10/7/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 10/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/12/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 10/12/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/25/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/26/2021 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/28/2021 | Approved | GREGG CUMMINGS |
| Insulation | 11/2/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 11/8/2021 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 11/19/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/24/2021 | Partial Approval | MICHEL ABAJAN |
| Service/Power Release | 12/1/2021 | Corrections Issued | GREGG CUMMINGS |
| Final | 12/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 12/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 12/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 12/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 12/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/25/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/25/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 2/25/2022 | Approved | GREGG CUMMINGS |
| Final | 4/12/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 4/20/2022 | OK to Issue CofO | GREGG CUMMINGS |