522 N GOWER ST 90004
Certificate Information: 522 N GOWER ST 90004
- Application / Permit
- 21014-20000-00739
- Plan Check / Job No.
- B21VN01904
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 27'-0" X 18'-7", 498 SQ. FT. ADDITION TO THE (E) SINGLE FAMILY DWELLING. ALL WORK SHALL CONFORM TO THE WFPP.
- Permit Issued
- Issued on 4/23/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | COLIN LOREDO |
| Corrections Issued | 3/6/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 4/7/2021 | RAHEL BEYENE |
| Plan Check Approved | 4/15/2021 | RAHEL BEYENE |
| Issued | 4/23/2021 | APPLICANT |
| Building Plans Picked Up | 4/27/2021 | APPLICANT |
| CofO in Progress | 10/2/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 10/6/2021 | DEROLD HAUFF |
| CofO Issued | 10/6/2021 | DEROLD HAUFF |
| Permit Finaled | 10/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/22/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 3/23/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/18/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/18/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 6/18/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 6/18/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/24/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 6/24/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 6/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/12/2021 | Approved | CHARLES BOGHOSKHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Partial Approval | CHARLES BOGHOSKHAN |
| HVAC-Rough | 7/12/2021 | Approved | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 7/12/2021 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | CHARLES BOGHOSKHAN |
| Green Building Rough | 7/14/2021 | Approved | CHARLES BOGHOSKHAN |
| Insulation | 7/14/2021 | Approved | CHARLES BOGHOSKHAN |
| METHANE-Rough | 7/14/2021 | Approved | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 7/14/2021 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 7/16/2021 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 7/16/2021 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 7/26/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Insulation | 7/26/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 9/21/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 9/21/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 9/21/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 9/21/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 9/21/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Final | 9/21/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/21/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 10/1/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 10/1/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 10/1/2021 | Approved | CHRIS CHRISTENSEN |