12456 W STANWOOD PL 90066
Certificate Information: 12456 W STANWOOD PL 90066
- Application / Permit
- 21014-20000-00738
- Plan Check / Job No.
- B21VN01901
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE-STORY DWELLING EXCEPT FOR 45 LF LONG, 13'7" LF LONG AND 11'7" LF LONG AT NORTH PORTION OF THE SITE AND BUILD AN IREEGULAR SHAPED 77' X 44'1" TWO STORY SINGLE FAMILY DWELLING WITH AN ATTACHED TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEEERING
- Permit Issued
- Issued on 7/26/2021
- Issuing Office
- Current Status
- CofO Issued on 4/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | RARES BODEA |
| Corrections Issued | 3/18/2021 | RARES BODEA |
| Quality Review Completed | 3/24/2021 | STEVEN KIM |
| Applicant returned to address corrections | 6/23/2021 | RARES BODEA |
| Building Plans Picked Up | 6/24/2021 | APPLICANT |
| Plan Check Approved | 7/20/2021 | RARES BODEA |
| Issued | 7/26/2021 | APPLICANT |
| CofO in Progress | 4/28/2022 | PATRICK QUALEY |
| Permit Finaled | 4/28/2022 | DANIEL ORRANTE |
| CofO Issued | 4/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 4/15/2021 | JOHN KIM |
| Specific Plan | Cleared | 4/27/2021 | PEDRO AYALA |
| Permit | Cleared | 5/19/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 5/19/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 6/12/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/14/2021 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 7/14/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 7/14/2021 | RARES BODEA |
Contact Information
| Contractor | Zepeda Juan; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/1/2021 | Partial Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 9/3/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/22/2021 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/27/2021 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Partial Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Approved | JOHN KAYON |
| ELECTRICAL-Rough | 12/15/2021 | Partial Approval | JOHN KAYON |
| Gas Test | 12/15/2021 | Approved | JOHN KAYON |
| HVAC-Rough | 12/15/2021 | Partial Approval | JOHN KAYON |
| PLUMBING-Rough | 12/15/2021 | Approved | JOHN KAYON |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/23/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/23/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/23/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/23/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 12/23/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 12/29/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/7/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/1/2022 | Approved | ENRIQUE MIRELES |
| Shower Pan | 2/1/2022 | Approved | ENRIQUE MIRELES |
| Gas Test | 3/14/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 4/14/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Final | 4/14/2022 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Final | 4/14/2022 | Corrections Issued | PATRICK QUALEY |
| Special/Order Compliance | 4/14/2022 | Partial Inspection | PATRICK QUALEY |
| ELECTRICAL-Final | 4/21/2022 | Approved | PATRICK QUALEY |
| Final | 4/21/2022 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 4/21/2022 | Approved | PATRICK QUALEY |
| HVAC-Final | 4/21/2022 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Final | 4/21/2022 | Approved | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Approved | PATRICK QUALEY |
| Smoke Detectors | 4/21/2022 | Approved | PATRICK QUALEY |
| Final | 4/25/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Final | 4/25/2022 | Approved | PATRICK QUALEY |
| Final | 4/28/2022 | OK to Issue CofO | PATRICK QUALEY |
| Service/Power Release | 4/28/2022 | Approved | PATRICK QUALEY |