15633-15635 W SIMONDS ST 91344

Certificate Information: 15633-15635 W SIMONDS ST 91344

Application / Permit
21014-20000-00706
Plan Check / Job No.
B21VN01837
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AND CONVERSION OF THE (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d). ALL WORK PER WFPP.
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 JAHANSHAH POURHASSAN
Corrections Issued 3/13/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/3/2021 OMAR GARNICA
Plan Check Approved 6/25/2021 OMAR GARNICA
Building Plans Picked Up 6/29/2021 APPLICANT
Issued 9/9/2021 APPLICANT
CofO in Progress 5/8/2023 JENNIFER RABUCHIN
Permit Finaled 5/11/2023 MICHAEL SMITH
CofO Issued 5/11/2023 MICHAEL SMITH
Permit Finaled 5/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/26/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 3/26/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 4/5/2021 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 4/30/2021 ADRIAN CASTRO
Sewer availability Cleared 4/30/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 5/17/2021 MATTHEW CRAIG

Contact Information

Contractor Yor Construction And Investments Inc; Lic. No.: 978430-B 12135 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 12/21/2021 Not Ready for Inspection MICHAEL TEMPLE
Underground Mechanical 12/21/2021 Not Ready for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 3/16/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 3/23/2022 Partial Approval JENNIFER RABUCHIN
Structural Steel Frame 3/23/2022 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/5/2022 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 5/5/2022 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 5/5/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/5/2022 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 5/5/2022 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/10/2022 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 5/10/2022 Corrections Issued MICHAEL TEMPLE
BUILDING-Rough-Frame 5/12/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/12/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/12/2022 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 5/12/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/16/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/16/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/16/2022 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/18/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/18/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/18/2022 Approved JENNIFER RABUCHIN
Insulation 5/25/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/8/2022 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 6/8/2022 Approved JENNIFER RABUCHIN
Green Building Rough 6/8/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/8/2022 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 6/15/2022 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 6/23/2022 Approved JENNIFER RABUCHIN
Shower Pan 6/23/2022 Approved JENNIFER RABUCHIN
Special/Order Compliance 6/23/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/11/2022 Approved JENNIFER RABUCHIN
Final 10/11/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 10/11/2022 Approved JENNIFER RABUCHIN
Green Building Final 10/11/2022 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 10/11/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/11/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 10/11/2022 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 10/11/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/10/2023 Corrections Issued JENNIFER RABUCHIN
Final 2/10/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/10/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/10/2023 SGSOV Not Ready JENNIFER RABUCHIN
ELECTRICAL-Final 3/21/2023 Corrections Issued JENNIFER RABUCHIN
Final 3/21/2023 Partial Inspection JENNIFER RABUCHIN
HVAC-Final 3/21/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/21/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/9/2023 Approved JENNIFER RABUCHIN
Final 5/9/2023 OK to Issue CofO JENNIFER RABUCHIN