7038-7040 N WHITAKER AVE 91406

Certificate Information: 7038-7040 N WHITAKER AVE 91406

Application / Permit
21014-20000-00698
Plan Check / Job No.
B21VN01811
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD ACCESSORY DWELLING UNIT ABOVE (E) SFD PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 1/6/2022
Issuing Office
Current Status
CofO Corrected on 3/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 MOHAMMAD ESMAILI
Corrections Issued 5/2/2021 MOHAMMAD ESMAILI
Quality Review Completed 5/12/2021 OMID HEDAYAT
Building Plans Picked Up 6/2/2021 APPLICANT
Applicant returned to address corrections 11/17/2021 MOHAMMAD ESMAILI
Plan Check Approved 12/22/2021 MOHAMMAD ESMAILI
Issued 1/6/2022 APPLICANT
CofO in Progress 2/21/2023 RAUL OLAGI
Re-Activate Permit 3/2/2023 MICHAEL SMITH
CofO Issued-Status Void 3/2/2023 MICHAEL SMITH
Permit Finaled-Status Void 3/2/2023 MICHAEL SMITH
Permit Finaled 3/2/2023 MICHAEL SMITH
CofO Corrected 3/2/2023 MICHAEL SMITH
Permit Finaled 3/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/29/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/29/2021 CARLOS AGUILERA
Sewer availability Cleared 6/29/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/11/2021 RUEL COLE
Low Impact Development Cleared 10/26/2021 SAHIL SHARMA
Roof/Waste drainage to street Cleared 10/26/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2022 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 3/7/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval ALAN MORELOS
Special/Order Compliance 6/15/2022 Corrections Issued ALAN MORELOS
Deputy Wood Construction 10/3/2022 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 10/11/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Approved RAUL OLAGI
PLUMBING-Rough 10/11/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/4/2022 Approved RAUL OLAGI
Green Building Rough 11/4/2022 Approved RAUL OLAGI
HVAC-Rough 11/4/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/4/2022 Not Ready for Inspection RAUL OLAGI
Insulation 11/14/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/14/2022 Partial Approval RAUL OLAGI
Drywall Nailing 11/23/2022 Approved RAUL OLAGI
Final 1/30/2023 Corrections Issued RAUL OLAGI
Green Building Final 1/30/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/30/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 1/30/2023 Approved RAUL OLAGI
Final 2/21/2023 OK to Issue CofO RAUL OLAGI